Data Center Fact Check tracks 1 data center project in Crittenden County, Arkansas as of November 2026.
Crittenden County has 1 tracked data center project. The project here is Google data center campus, West Memphis, under construction. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in Crittenden County
- Google data center campus, West Memphis
Under constructionWest Memphis
Who serves this place
- Not collected yet.
Places in and around Crittenden County
Crittenden County is part of Arkansas.
Cities and towns
- West Memphis1 data center project tracked
Nearby places
- Pulaski County3 data center projects tracked
- Faulkner County1 data center project tracked
- Johnson County1 data center project tracked
- Union County1 data center project tracked
Court cases and commission dockets in Arkansas (5)
Bills and laws in Arkansas
- HR 1013 · Died or failed · Apr 29, 2026Would have authorized a 2026 bill rewriting the Data Centers Act mining rules
- SB 11 · Died or failed · May 5, 2025Amends the Data Centers Act and money services law
- SB 10 · Died or failed · May 5, 2025Lets state agencies halt mining operations over water and grid harm
- HB 1444 · Signed into law · Apr 10, 2025Cuts the data center tax exemption investment threshold to $100 million
- SB 78 · Signed into law · May 3, 2024Sets mining noise rules and bars prohibited foreign parties from owning Arkansas mining businesses
- SB 79 · Signed into law · May 3, 2024Creates Oil and Gas Commission permitting for digital asset mining businesses
- HB 1476 · Died or failed · May 1, 2023Would have exempted electricity sold to a data center from sales and use tax
- HB 1477 · Died or failed · May 1, 2023Would have exempted certain data centers from storm recovery costs and charges
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Crittenden County?
- Data Center Fact Check tracks 1 data center project in Crittenden County as of November 2026.
Sources
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Crittenden County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ar-crittenden