TennesseeHouse of Representatives114th General AssemblyBill
HB 1847: Bars utilities from absorbing data center electrical infrastructure costs
Official title: AN ACT to amend Tennessee Code Annotated, Title 5; Title 6; Title 7; Title 13 and Title 65, relative to data centers
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
In effect as of May 7, 2026. The official record says: Public Chapter 961.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (done)
- Signed into law (done)
- In effect (current stage)
What it does
Who pays for grid costs
Applies to: municipalities and electric utilities serving a data center (Tennessee)
“Except as otherwise provided in this section, a municipality or electric utility shall not pay, or otherwise absorb, the cost of electrical infrastructure incurred to serve a data center.”
SECTION 1, TCA 7-70-102(a)
Definition · threshold 50 MW
Applies to: data centers covered by TCA Chapter 7-70 (Tennessee)
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.”
SECTION 1, TCA 7-70-101(2)(A)(ii)
Effective date
Applies to: the whole act (Tennessee)
Starts: 2026-05-07.
“This act takes effect upon becoming a law, the public welfare requiring it, and applies to conduct occurring and contracts or agreements entered into, amended, or renewed on or after that date.”
SECTION 4
Service terms
Applies to: data centers buying power from in-state independent power producers (Tennessee)
“A data center may purchase and receive electric energy, capacity, or other related or ancillary services from an independent power producer located in this state.”
SECTION 1, TCA 7-70-102(e)
Who it touches (14)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 20265C MEM01
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Bitdeer Knoxville
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has 86 MW on record (grid connection), but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee; 86 MW on record (grid connection), threshold 50 MW (SECTION 1, TCA 7-70-101(2)(A)(ii)). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CleanSpark Limestone (GRIID)
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Cogent Memphis Edge Data Center
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Connect Memphis (Oppidan)
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Csquare Nashville BNA1 (Gallatin)
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DC BLOX Nashville (Grassmere Park)
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026GRIID Lenoir City (CleanSpark)
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026GRIID Maynardville (CleanSpark)
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Google Montgomery County Data Center
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Litewire McMinnville
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Meta Gallatin Data Center
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026xAI Colossus (Memphis)
On status, the bill was enacted as Public Chapter 961 and is in effect, which sets the May 7, 2026 date the act applies from; on the text, the act covers a building that primarily contains electronic equipment used to process, store, or transmit digital information and is projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, and bars a municipality or electric utility from paying or absorbing its electrical infrastructure costs; this project is an operating data center in Memphis, Tennessee, with 300 MW of grid electric service requested on record, but no staged fact states its projected peak electric demand during its first three years of operation.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee; 300 MW on record (grid connection), threshold 50 MW (SECTION 1, TCA 7-70-101(2)(A)(ii)). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026xAI Colossus 2 (Memphis, Whitehaven)
On status, the bill was enacted as Public Chapter 961 and is in effect, which sets the May 7, 2026 date the act applies from; on the text, the act covers a building that primarily contains electronic equipment used to process, store, or transmit digital information and is projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, and bars a municipality or electric utility from paying or absorbing its electrical infrastructure costs; this project is an operating data center in Memphis, Tennessee, with 430 MW of it load on record in two clusters brought online, but no staged fact states its projected peak electric demand during its first three years of operation.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee; 430 MW on record (announced), threshold 50 MW (SECTION 1, TCA 7-70-101(2)(A)(ii)). Still to check: dates: not checked, who it covers: not checked
Other projects we track in Tennessee (7), not affected
- DataBank Memphis (MEM1)Operating
- DC BLOX Chattanooga (CHA1)Operating
- EdgeConneX Memphis (MEM01)Operating
- Expedient MemphisOperating
- Flexential Nashville - BrentwoodOperating
- Flexential Nashville - Cool SpringsOperating
- Flexential Nashville - FranklinOperating
Who acted
- CosponsorBarrettHouse
- CosponsorHawkHouse
- CosponsorHowellHouse
- CosponsorReneauHouse
- Primary sponsorButlerHouse
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- · HouseHouse Commerce Committee: Rec. for pass. if am., ref. to Finance, Ways, and Means CommitteeStage: In committee
- · HouseFloor vote: passage on third consideration as amended, Ayes 76, Noes 14Stage: Passed one chamber
- Passed (Public Chapter 961 header: PASSED: April 22, 2026)Stage: Passed both chambers
- Approved by Governor Bill LeeStage: Signed into law
More from Tennessee
- HB 2061 · Died or failedRequires data centers to register and report power and water use
- SB 1682 · Died or failedRequires data centers to register and report power and water use
- SB 2128 · Signed into lawBars utilities from absorbing data center electrical infrastructure costs
- SB 1832 · Died or failedRequires computing facilities to devote half their output to public benefit
- SB 2584 · Died or failedLets qualified data centers certify compliance for job tax credits
- SB 1999 · Died or failedMakes large data centers help fund grid upgrades through tariffs
Sources
- 1Bill Information: HB1847 by Butler (114th General Assembly)
Tennessee General AssemblyTier 1 · Open the source - 2
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "HB 1847: Bars utilities from absorbing data center electrical infrastructure costs." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/tn-114-hb-1847
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page