DC BLOX Nashville (Grassmere Park)
Nashville-Davidson metropolitan government (balance),Davidson County,TennesseeIn permittingFirst public 2025Filing entity: DCB Nashville, LLCLast checked Nov 8, 2026
DC BLOXDeveloperBurr Computer EnvironmentsBuilder
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
DC BLOX Nashville (Grassmere Park) is a data center project in Nashville-Davidson metropolitan government (balance), Davidson County, Tennessee. DC BLOX is named as developer. It is in permitting. It was first public in 2025. No site capacity figure is published for this project.
DC BLOX Nashville (Grassmere Park) is a data center project in Nashville-Davidson metropolitan government (balance), Davidson County, Tennessee. DC BLOX is named as developer. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Nashville-Davidson metropolitan government (balance), Davidson County, Tennessee. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

The land, to scale
Timeline
- · New projectFirst public record of DC BLOX Nashville (Grassmere Park)In permitting
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Tennessee HB 1847: Bars utilities from absorbing data center electrical infrastructure costs
The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.
“Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))
Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked
Bills and laws in Tennessee
- HB 2061 · Died or failedRequires data centers to register and report power and water use
- SB 1682 · Died or failedRequires data centers to register and report power and water use
- SB 2128 · Signed into law · May 18, 2026Bars utilities from absorbing data center electrical infrastructure costs
- HB 1847 · In effect · May 7, 2026Bars utilities from absorbing data center electrical infrastructure costs
- SB 1832 · Died or failed · Mar 10, 2026Requires computing facilities to devote half their output to public benefit
- SB 1999 · Died or failed · Mar 10, 2026Makes large data centers help fund grid upgrades through tariffs
Who's involved
- DeveloperDC BLOX
- BuilderBurr Computer Environments
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is DC BLOX Nashville (Grassmere Park)?
- DC BLOX Nashville (Grassmere Park) is a data center project in Nashville-Davidson metropolitan government (balance), Davidson County, Tennessee.
- Who is developing DC BLOX Nashville (Grassmere Park)?
- DC BLOX is named as the developer of DC BLOX Nashville (Grassmere Park).
- How big is DC BLOX Nashville (Grassmere Park)?
- The site covers 23.49 acres.
- What stage is DC BLOX Nashville (Grassmere Park)?
- DC BLOX Nashville (Grassmere Park) is in permitting. It was first public in 2025.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Memorandum Opinion, DCB Nashville, LLC v. Metropolitan Government of Nashville and Davidson County, No. 3:26-cv-01143 (M.D. Tenn., Oct. 6, 2026)
U.S. District Court for the Middle District of TennesseeTier 1 · Captured 2026-11-08 · Open the source - 2Mayor Freddie O'Connell's Message to Metro Council Regarding Tuesday's Data Center Legislation
Metropolitan Government of Nashville and Davidson County (Office of the Mayor)Tier 1 · Captured 2026-11-08 · Open the source - 3U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source - 4EIA Form 861, Service Territory file, 2025 (final)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-11 · Open the source · Archived copy
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page