Project File
DataBank Memphis (MEM1)
Memphis,Shelby County,TennesseeOperatingFiling entity: DataBankLast checked Nov 8, 2026
DataBankOperator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: Electric utility
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
DataBank Memphis (MEM1) is an operating data center project in Memphis, Shelby County, Tennessee. DataBank is named as operator. It was announced at 0.45 MW.
DataBank Memphis (MEM1) is an operating data center project in Memphis, Shelby County, Tennessee. DataBank is named as operator. It was announced at 0.45 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Memphis, Shelby County, Tennessee. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Newswire for Shelby County
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 28, 2026
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Bills and laws in Tennessee
- HB 2061 · Died or failedRequires data centers to register and report power and water use
- SB 1682 · Died or failedRequires data centers to register and report power and water use
- SB 2128 · Signed into law · May 18, 2026Bars utilities from absorbing data center electrical infrastructure costs
- HB 1847 · In effect · May 7, 2026Bars utilities from absorbing data center electrical infrastructure costs
- SB 1832 · Died or failed · Mar 10, 2026Requires computing facilities to devote half their output to public benefit
- SB 1999 · Died or failed · Mar 10, 2026Makes large data centers help fund grid upgrades through tariffs
Who's involved
- OperatorDataBank
Power
Capacity, as announced or filed
- 0.45 MW · Facility totalNov 2026 · it_load
Public records
3 records found so far. 6 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · In effect · Oct 1, 2026Electric Service Schedule TDC, Time of Use Data Service
Questions people ask
- Where is DataBank Memphis (MEM1)?
- DataBank Memphis (MEM1) is a data center project in Memphis, Shelby County, Tennessee.
- Who operates DataBank Memphis (MEM1)?
- DataBank is named as the operator of DataBank Memphis (MEM1).
- How big is DataBank Memphis (MEM1)?
- DataBank Memphis (MEM1) was announced at 0.45 MW of capacity.
- What stage is DataBank Memphis (MEM1)?
- DataBank Memphis (MEM1) is operating.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Memphis City Council regular agenda October 20 2026
City of MemphisTier 1 · Captured 2026-11-08 · Open the source - 2Electric Service Schedule TDC, Time of Use Data Service (rate effective October 1, 2026)
Memphis Light, Gas and Water Division, City of MemphisTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 3Minutes, Meeting of the City Council, City of Memphis, August 19, 2025
City of MemphisTier 1 · Captured 2026-11-09 · Open the source - 47620 Appling Center Drive, Memphis Data Center (MEM1)
DataBankTier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page