Cogent Memphis Edge Data Center

Memphis,Shelby County,TennesseeOperatingLast checked Nov 10, 2026

Cogent CommunicationsOperator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Electric utility
  • Still to confirm: Capacity
  • Still to confirm: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Cogent Memphis Edge Data Center is an operating data center project in Memphis, Shelby County, Tennessee. Cogent Communications is named as operator. No site capacity figure is published for this project.

Cogent Memphis Edge Data Center is an operating data center project in Memphis, Shelby County, Tennessee. Cogent Communications is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Memphis, Shelby County, Tennessee. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

3Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Newswire for Shelby County

  1. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  2. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Aerial view of Cogent Memphis Edge Data Center (Cogent Communications) in Memphis, Shelby County, Tennessee, captured 2021
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2021Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Shelby County, Tennessee.See every project on the map

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Tennessee HB 1847: Bars utilities from absorbing data center electrical infrastructure costs

    The act covers data centers projected to have a peak electric demand of fifty megawatts or more during the first three years of operation, whose electrical infrastructure costs a municipality or electric utility may not pay or absorb, for conduct and contracts on or after May 7, 2026; this project has no capacity figure on record, but the project's projected peak electric demand during its first three years of operation is not on record.

    “Is projected to have a peak electric demand of fifty megawatts (50 MW) or more during the first three (3) years of operation.” (SECTION 1, TCA 7-70-101(2)(A)(ii))

    Rule checks: Project is in Tennessee. Still to check: size: unknown, dates: not checked, who it covers: not checked

Bills and laws in Tennessee

All 12 in Bill Watch

Who's involved

Public records

3 records found so far. 6 kinds of record are still being collected.

See every record

Court cases and commission dockets

Questions people ask

Where is Cogent Memphis Edge Data Center?
Cogent Memphis Edge Data Center is a data center project in Memphis, Shelby County, Tennessee.
Who operates Cogent Memphis Edge Data Center?
Cogent Communications is named as the operator of Cogent Memphis Edge Data Center.
What stage is Cogent Memphis Edge Data Center?
Cogent Memphis Edge Data Center is operating.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Memphis City Council regular agenda October 20 2026
    City of Memphis
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Electric Service Schedule TDC, Time of Use Data Service (rate effective October 1, 2026)
    Memphis Light, Gas and Water Division, City of Memphis
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy
  3. 3
    Minutes, Meeting of the City Council, City of Memphis, August 19, 2025
    City of Memphis
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Memphis Edge Data Center brochure (2632 Jackson Avenue) — Cogent Communications
    Cogent Communications
    Tier 4 · Captured 2026-11-10 · Open the source
  5. 5
    EIA Form 861, Service Territory file, 2025 (final)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page