Project File · Public records
Every public record we have for Cogent Memphis Edge Data Center
Memphis, Shelby County, TennesseeOperatingLast checked Nov 10, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
1 of 3 records · showing land and zoning rules only ·
2026
Development ruleIn effectOct 20, 2026Memphis
135-day pause on new data center development with directions for permanent rules
Memphis paused new data center development for 135 days and directed its planning division to draft permanent Unified Development Code amendments for data centers within 90 days with council guidelines for the permanent rules; existing facilities are not stopped. The separate 18-month moratorium (Ordinance No. 5982) failed on a 6-6 tie the same night.
Ordinance No. 5986 (substitute adopted 2026-10-20)
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
City Council regular agenda for 2026-10-20 items 18 (Ordinance 5986 third and final reading) and 19 (Ordinance 5982 moratorium)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Memphis City Council regular agenda October 20 2026
City of MemphisTier 1 · Captured 2026-11-08 · Open the source - 2Electric Service Schedule TDC, Time of Use Data Service (rate effective October 1, 2026)
Memphis Light, Gas and Water Division, City of MemphisTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 3Minutes, Meeting of the City Council, City of Memphis, August 19, 2025
City of MemphisTier 1 · Captured 2026-11-09 · Open the source - 4Memphis Edge Data Center brochure (2632 Jackson Avenue) — Cogent Communications
Cogent CommunicationsTier 4 · Captured 2026-11-10 · Open the source - 5EIA Form 861, Service Territory file, 2025 (final)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-11 · Open the source · Archived copy
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page