State Card
Data centers in Kansas
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 11 data center projects in Kansas as of November 2026: 7 operating, 2 approved and 1 proposed, totaling about 2,633 MW announced where a figure is published.
Kansas has 11 tracked data centers. Their announced capacity totals about 2,633 MW where a figure is published. Of those, 7 operating, 2 approved and 1 proposed. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in Kansas
- Beale Infrastructure data center campus, Project Pilot (De Soto)
ApprovedDe Soto
- Cloverleaf Infrastructure data center, Project Bluestem (Leavenworth County)
ProposedTonganoxie
- DataBank MCI2 (Kansas City)
OperatingOverland Park2 MW announced
- DataBank MCI3 (Kansas City)
OperatingLenexa13 MW announced
- DataBank Pine Ridge Data Center (MCI2, Overland Park)
OperatingOverland Park2 MW announced
- DataBank South Lake Campus (MCI1 and MCI3, Lenexa)
OperatingLenexa13 MW announced
- Digital Realty data center campus, Astra Enterprise Park (De Soto)
ApprovedDe Soto2,000 MW announced
- LightEdge data center, Lenexa (Cavern Technologies underground facility)
OperatingLenexa3 MW announced
- Netrality KC2 (7801 Nieman)
OperatingShawnee
- Red Wolf DCD Properties data center campus (Kansas City, Kansas)
In permittingKansas City600 MW announced
- TierPoint Kansas City - Lenexa (LEN)
OperatingLenexa
Who serves this place
- Not collected yet.
Counties and cities in Kansas
Counties
- Johnson County9 data center projects tracked
- Leavenworth County1 data center project tracked
- Wyandotte County1 data center project tracked
Cities and towns
- Lenexa4 data center projects tracked
- De Soto2 data center projects tracked
- Overland Park2 data center projects tracked
- Kansas City1 data center project tracked
- Shawnee1 data center project tracked
- Tonganoxie1 data center project tracked
Tax breaks and payments
Sales tax exemption, qualified data centers (2025 Senate Bill 98)
A qualified firm certified by the Secretary of Commerce is exempt from state and local sales tax on purchases related to the construction, reconstruction, enlarging, or remodeling of a qualified data center, covering eligible data center costs, and on labor services to install, apply, repair, service, alter, or maintain data center equipment. The exemption is valid for 20 years after the commencement of operations. Senate Bill 98 put the exemption in K.S.A. 79-3606 and the program in new sections administered by the Department of Commerce; the Department of Revenue's Notice 25-03 (July 3, 2025) implements it, and the Revenue Department issues the project exemption certificate on Commerce's certification.
Recent cases and dockets in Kansas
- Utility commission · DecidedApplication of Evergy Kansas Central, Inc. and Evergy Metro, Inc. for approval of a large load power service rate plan (LLPS)
- Utility commission · DecidedApplication of Evergy Kansas Central, Inc. and Evergy Metro, Inc. for approval of a large load power service rate plan (LLPS)
Bills and laws in Kansas
- SB 400 · Died or failedClosed loop cooling required for large data centers
- SB 526 · Died or failedExemption only for data centers on industrial zoned land
- SB 531 · Died or failedNo new large data centers in drought emergency counties
- SB 98 · Signed into law · Apr 24, 2025Sales tax exemption for large Kansas data centers
- SB 51 · Died or failed · Mar 27, 2025Original data center sales tax exemption bill
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Kansas?
- Data Center Fact Check tracks 11 data center projects in Kansas as of November 2026. Of those, 7 operating, 2 approved and 1 proposed.
- What is the biggest data center in Kansas?
- By announced capacity, the biggest data center in Kansas is Digital Realty data center campus, Astra Enterprise Park (De Soto), announced at 2,000 MW. It is approved.
- How much power do data centers in Kansas use?
- The 11 projects tracked in Kansas have announced about 2,633 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1SB 98 Data Center Sales Tax Exemption (program page)
Kansas Department of CommerceTier 1 · Open the source - 2SB 98, 2025 Summary of Legislation (Qualified Data Center Sales Tax Exemption)
Kansas Legislative Research DepartmentTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Kansas." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ks
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page