Jeffersonville,Clark County,IndianaUnder constructionFirst public 2024Last checked Nov 8, 2026
MetaDeveloper and operatorTurner ConstructionBuilderDuke Energy IndianaElectric utilityRiver Ridge Development AuthorityPublic partner
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Meta Jeffersonville Data Center is a under-construction data center project in Jeffersonville, Clark County, Indiana. Meta is named as operator. It was first public in 2024. No site capacity figure is published for this project.
Meta Jeffersonville Data Center is an under-construction data center project in Jeffersonville, Clark County, Indiana. Meta is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Jeffersonville, Clark County, Indiana. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
- Property tax
The City Council approved a property tax exemption agreement in 2022; the minutes state neither its length nor its size.
Goes both ways - Tax breaks
The state announced a sales tax exemption on campus equipment with the project in 2024.
Comes to the community - Money for schools and services
No community payment from this project is in our records.
Not known yet - Electricity bill
The average Duke Energy Indiana home paid $148.57 a month in 2025, up from $117.55 in 2016, not adjusted for inflation.
Not known yet - Water
Indiana American Water serves Jeffersonville; no record we found names the provider for the campus parcel itself.
Not known yet - Jobs
Job counts for this campus are not in our records yet.
Not known yet - Next door: height, setbacks, noise
The city paused other new data centers for one year in August 2026; the pause does not cover this campus.
Local rule - Your say
The City Council approved the campus tax agreement in a public vote on September 19, 2022.
How to take part
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · DecisionIndiana Economic Development Corporation: 35-year data center sales tax exemption committed for a minimum $800 million in eligible capital, plus 5 years per additional $800 million up to a 50-year total term (tax agreement) for Meta Jeffersonville Data Center
- · FilingFiled with Indiana Economic Development Corporation: tax agreement for Meta Jeffersonville Data Center
- · New projectFirst public record of Meta Jeffersonville Data CenterUnder construction
- · Court caseCourt case filed: Verified Petition of Duke Energy Indiana, LLC for Approval of a Special Retail Electric Service Agreement, Renewable Energy Purchase Agreement, and Tranche Agreements with Blocke, LLCIndiana Utility Regulatory Commission
- · FilingFiled with Indiana Utility Regulatory Commission for Meta Jeffersonville Data CenterCause No. 45975
- · DecisionCity of Jeffersonville Common Council: Approved, 8-0 roll call (tax agreement) for Meta Jeffersonville Data CenterResolution 2022-R-10
- · Tax dealTax agreement approved: Development agreement, titled a property tax exemption agreement (resolution 2022-r-10)
- · VoteJeffersonville Common Council voted on Resolution 2022-R-10: Development Agreement for a data center project (Project Slugger), property tax exemption agreement8 yes, 1 absent
Bills and laws in Indiana
- HB 1333 · Passed one chamber · Feb 5, 2026Requires local agreement before data centers use a state tax exemption
- SB 257 · In committee · Jan 8, 2026Would bar the state commission from approving an electric rate increase to the extent it is related solely to the cost of serving a data center or a large facility with fewer than 50 full-time employees
- SB 79 · In committee · Jan 6, 2026Would require a state working group estimate of data center electricity demand, quarterly electricity-use reports from operators, and local permit disclosure of projected power and water use
- HB 1189 · In committee · Jan 5, 2026Would require a state incentive agreement with a qualified data center user to limit project bids and requests for proposals to labor unions or employers that have project labor agreements
- HB 1245 · In committee · Jan 5, 2026Requires a state study of data center demand effects on rates
- SB 83 · In committee · Dec 8, 2025Broad utility bill whose one data center provision repeals the sales and use tax exemption for certain data centers enacted in the 2025 session in HEA 1601
Who's involved
- Developer and operatorMeta
- BuilderTurner Construction
- Electric utilityDuke Energy Indiana
- Public partnerRiver Ridge Development Authority
From the filings
Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.
City of Jeffersonville Common Council, Resolution 2022-R-10
- Stated in the filing
- 600 acres (approximately, as presented to the Council)
- Estimated cost
- $800 million at least, as presented; possibly close to $1 billion at completion
Indiana Economic Development Corporation
- Estimated cost
- $800 million minimum eligible capital under the sales tax exemption
- Floor area
- 700,000 sq ft (nearly 700,000, as announced)
- Stated in the filing
- 619 acres (site at River Ridge Commerce Center)
Public records
10 records found so far. 5 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Decided · Oct 31, 2023Verified Petition of Duke Energy Indiana, LLC for Approval of a Special Retail Electric Service Agreement, Renewable Energy Purchase Agreement, and Tranche Agreements with Blocke, LLC
- Court case · Decided · Oct 31, 2023Verified Petition of Duke Energy Indiana, LLC for Approval of a Special Retail Electric Service Agreement, Renewable Energy Purchase Agreement, and Tranche Agreements with Blocke, LLC
Questions people ask
- Where is Meta Jeffersonville Data Center?
- Meta Jeffersonville Data Center is a data center project in Jeffersonville, Clark County, Indiana.
- Who operates Meta Jeffersonville Data Center?
- Meta is named as the operator of Meta Jeffersonville Data Center.
- How big is Meta Jeffersonville Data Center?
- The site covers 619 acres.
- What stage is Meta Jeffersonville Data Center?
- Meta Jeffersonville Data Center is under construction. It was first public in 2024.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Common Council Regular Meeting Minutes, September 19, 2022
City of JeffersonvilleTier 1 · Captured 2026-11-07 · Open the source - 2Electricity Rate Designs for Large Loads: Evolving Practices and Opportunities
Lawrence Berkeley National LaboratoryTier 2 · Captured 2026-11-07 · Open the source - 3Gov. Holcomb announces Meta to build an $800M Data Center Campus in Indiana (IEDC release, January 25, 2024)
Indiana Economic Development Corporation (via GlobeNewswire)Tier 4 · Captured 2026-11-08 · Open the source - 4Clark County, Indiana Code of Ordinances, Section 156.28 (M1 Light Industrial)
Clark County, Indiana (American Legal Publishing)Tier 1 · Captured 2026-11-07 · Open the source - 5Jeffersonville Unified Development Ordinance (revised September 9, 2026)
City of JeffersonvilleTier 1 · Captured 2026-11-08 · Open the source - 6Jeffersonville passes year-long data center moratorium
WDRB / WAVE (Louisville)Tier 3 · Captured 2026-11-07 · Open the source - 72026 Zoning Update handout
City of Jeffersonville, IndianaTier 1 · Captured 2026-11-07 · Open the source - 8Jeffersonville data center zoning explained: How Meta got approved
Rural News NetworkTier 3 · Captured 2026-11-07 · Open the source - 9
- 10EIA Form 861 2025, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-07 · Open the source - 11EIA Form 861 2016, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-07 · Open the source - 122024 Annual Water Quality Report, Southern Indiana Operations (PWS ID IN5210005)
Indiana American WaterTier 4 · Captured 2026-11-08 · Open the source - 13Turner Construction Company to Build Hyperscale Data Center for Meta in Indiana
Turner Construction CompanyTier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page