County Card

Data centers in Clark County, Indiana

Last checked Nov 7, 2026

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 1 data center project in Clark County, Indiana as of November 2026.

Clark County has 1 tracked data center project. Electricity here comes from Clark County REMC. The project here is Meta Jeffersonville Data Center, under construction. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.

1Data center project we track
0.5315Real property tax rate, USD per 100 USD of assessed value, 2026

Data center projects in Clark County

Who serves this place

  • ElectricityClark County REMC
  • ElectricityDuke Energy Indiana, LLC
  • WaterIndiana American Water
  • WaterRiver Ridge water system
  • Grid regionMISO

Places in and around Clark County

Clark County is part of Indiana.

Cities and towns

Nearby places

For homeowners

What the projects here mean if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    • The City Council approved a property tax exemption agreement in 2022; the minutes state neither its length nor its size.

      Goes both ways
  2. Tax breaks

    • The state announced a sales tax exemption on campus equipment with the project in 2024.

      Comes to the community
  3. Money for schools and services

    • No community payment from this project is in our records.

      Not known yet
  4. Electricity bill

    • The average Duke Energy Indiana home paid $148.57 a month in 2025, up from $117.55 in 2016, not adjusted for inflation.

      Not known yet
  5. Water

    • Indiana American Water serves Jeffersonville; no record we found names the provider for the campus parcel itself.

      Not known yet
  6. Jobs

    • Job counts for this campus are not in our records yet.

      Not known yet
  7. Next door: height, setbacks, noise

    • The city paused other new data centers for one year in August 2026; the pause does not cover this campus.

      Local rule
  8. Your say

    • The City Council approved the campus tax agreement in a public vote on September 19, 2022.

      How to take part

Taxes and budget over time

As published by the county, not adjusted for inflation. Projections are labeled.

Total property tax revenue

Total property tax revenue by year
2025$29.3 million
2024$26.4 million
2023$25.8 million
2022$25.1 million
2021$25.5 million
2020$23.4 million

Real property tax rate

Real property tax rate by year
20260.5315 USD per 100 USD of assessed value
20250.5247 USD per 100 USD of assessed value
20240.5543 USD per 100 USD of assessed value
20230.556 USD per 100 USD of assessed value
20220.6143 USD per 100 USD of assessed value
20210.6161 USD per 100 USD of assessed value

Total assessed value

Total assessed value by year
2026$6.54 billion
2025$6.1 billion
2024$5.73 billion
2023$4.87 billion
2022$4.34 billion
2021$4.04 billion

General fund budget

General fund budget by year
2026$39.0 million
2025$37.9 million
2024$36.2 million
2023$33.4 million
2022$33.7 million
2021$28.7 million

Tax breaks and payments

Local rules for data centers

  • In effect · Moratorium · Adopted Aug 3, 2026

    One year moratorium on new data center development

    The moratorium halts new data center development in the city for one year while the Plan Commission drafts permanent zoning rules for the Unified Development Ordinance. The administration proposed six months and the council extended it to a full year. It does not affect the Meta data center under construction at the River Ridge Commerce Center, because the River Ridge Development Authority holds zoning authority over that land under a long standing interlocal agreement, and the city's own 2026 zoning update handout confirms data center zoning is being handled in a separate later ordinance because of the moratorium.

  • In effect · Zoning · Adopted Dec 18, 2007

    Data processing or analysis is a permitted use in the M1 Light Industrial district, and in M2 through the M1 list

    The M1 Light Industrial district permits, by right, engineering or research laboratories, vocational or industrial training facilities, and data processing or analysis, along with a catch all for other comparable and compatible uses. The M2 Heavy Industrial district permits any use permitted in the M1 district, except day care centers and churches, so the same data processing use carries into M2. The county code has no definition of data center or data processing center, so a modern data center would rest on this data processing wording or the comparable use clause.

  • In effect · Setback · Adopted Dec 18, 2007

    A 250 foot setback where an M1 lot faces or abuts residential zoning, plus road based front setbacks and a height rule

    Where a front, side, or rear industrial lot line faces land zoned A1, RP, R1, or R2 across a street, or abuts any of those districts, the minimum setback is 250 feet, and that area may be used only for driveways and parking and must be landscaped with opaque fencing and natural buffer material. Front setbacks otherwise run from the road by road class, and building height is capped at 40 feet unless extra setback is traded for height up to 100 feet.

  • In effect · Generator

    Commercial generators must be enclosed and screened; no testing, fuel, or emissions rules found

    The UDO treats commercial generators as accessory structures and requires generators and mechanical equipment over the size threshold to be enclosed and screened, with screening on all sides by a fence or wall built to match the primary building. The ordinance sets no generator testing hours, fuel rules, emissions limits, or generator noise limits in the text searched. The UDO contains no data center use at all: full text searches for "data center" and "data processing" returned no hits.

Court cases and commission dockets in Indiana (7)

Bills and laws in Indiana

Open Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in Clark County?
Data Center Fact Check tracks 1 data center project in Clark County as of November 2026.

Sources

  1. 1
    2024 Annual Water Quality Report, Southern Indiana Operations (PWS ID IN5210005)
    Indiana American Water
    Tier 4 · Open the source
  2. 2
    River Ridge Water System
    River Ridge Development Authority
    Tier 1 · Open the source
  3. 3
    Electricity Rate Designs for Large Loads: Evolving Practices and Opportunities
    Lawrence Berkeley National Laboratory
    Tier 2 · Open the source
  4. 4
    MISO Market Participants, February 2026 certified list
    Midcontinent Independent System Operator (MISO)
    Tier 1 · Open the source
  5. 5
    Get to Know District 7
    Clark County REMC
    Tier 1 · Open the source
  6. 6
    Indiana Gateway budget data downloads
    Indiana Gateway
    Tier 1 · Open the source
  7. 7
    Indiana Gateway Annual Financial Report data downloads
    Indiana Gateway
    Tier 1 · Open the source
  8. 8
    Common Council Regular Meeting Minutes, September 19, 2022
    City of Jeffersonville
    Tier 1 · Open the source
  9. 9
    Gov. Holcomb announces Meta to build an $800M Data Center Campus in Indiana (IEDC release, January 25, 2024)
    Indiana Economic Development Corporation (via GlobeNewswire)
    Tier 4 · Open the source
  10. 10
    EIA Form 861 2025, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Open the source
  11. 11
    EIA Form 861 2016, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Open the source
  12. 12
    Jeffersonville passes year-long data center moratorium
    WDRB / WAVE (Louisville)
    Tier 3 · Open the source
  13. 13
    Jeffersonville data center zoning explained: How Meta got approved
    Rural News Network
    Tier 3 · Open the source
  14. 14
    2026 Zoning Update handout
    City of Jeffersonville, Indiana
    Tier 1 · Open the source
  15. 15
    Clark County, Indiana Code of Ordinances, Section 156.28 (M1 Light Industrial)
    Clark County, Indiana (American Legal Publishing)
    Tier 1 · Open the source
  16. 16
    Jeffersonville Unified Development Ordinance (revised September 9, 2026)
    City of Jeffersonville
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.