What it is
Duke Energy Indiana asked the IURC to approve a 20-year special retail electric service agreement with Blocke, LLC, the Meta entity for the Jeffersonville data center, instead of serving the campus under a standard tariff. Under the agreement Duke procures renewable power for the customer through dedicated purchase agreements that are not system resources and are not in Duke's integrated resource plan, and the customer pays its share of transmission costs, including upgrades, through the open access transmission tariff.
The facts
- Court
- Indiana Utility Regulatory Commission
- Docket number
- Cause No. 45975
- Place
- Clark County
- State
- Indiana
- Filed
- Oct 31, 2023
The project it is about
Related cases and proceedings
- Utility commission · DecidedVerified Petition of NIPSCO Generation LLC for Certain Determinations by the Commission with Respect to Its Jurisdiction Over Petitioner's Activities as a Non-Retail Generator of Electric Power
- Utility commission · DecidedVerified Petition of Indiana Michigan Power Company for Approval of Modifications to Its Industrial Power Tariff, Tariff I.P.
- Court case · DecidedIndiana Michigan Power large load tariff settlement
- Utility commission · DecidedVerified Petition of Duke Energy Indiana, LLC for Approval of a Special Retail Electric Service Agreement, Renewable Energy Purchase Agreement, and Tranche Agreements with Blocke, LLC
In the record
- Court case, Oct 31, 2023. Court case filed: Verified Petition of Duke Energy Indiana, LLC for Approval of a Special Retail Electric Service Agreement, Renewable Energy Purchase Agreement, and Tranche Agreements with Blocke, LLC Indiana Utility Regulatory Commission
Sources
- 1Electricity Rate Designs for Large Loads: Evolving Practices and Opportunities
Lawrence Berkeley National LaboratoryTier 2 · LBNL, Electricity Rate Designs for Large Loads (January 2025), appendix entry for Cause No. 45975 and the contract summary (20-year term; renewable procurement; transmission cost share) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Verified Petition of Duke Energy Indiana, LLC for Approval of a Special Retail Electric Service Agreement, Renewable Energy Purchase Agreement, and Tranche Agreements with Blocke, LLC." Last activity 2023-10-31. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/cases/case-in-iurc-45975