Verified Petition of NIPSCO Generation LLC for Certain Determinations by the Commission with Respect to Its Jurisdiction Over Petitioner's Activities as a Non-Retail Generator of Electric Power

Where it stands: Decided as of Sep 24, 2025

Draft research, not yet verified. Open a source to check any detail.

What it is

Framework order for NIPSCO’s data center generation affiliate. The Commission granted NIPSCO Generation LLC (GenCo) a limited declination of jurisdiction so it may purchase, construct, own and operate generation to serve NIPSCO megaload and data center customers, ring-fencing those generation costs from existing NIPSCO retail customers. For each megaload customer GenCo must make a Construction Compliance Filing at least 30 days before starting construction. Affiliate service agreements were filed as 30-Day Filing 50863, effective October 27, 2025. An order on reconsideration on November 19, 2025 removed GenCo’s eminent domain authority.

The facts

Regulator
Indiana Utility Regulatory Commission
Docket number
Cause No. 46183
Type
Other
Utility
Northern Indiana Public Service Company
State
Indiana
Status date
Sep 24, 2025
Large-load rules
Yes

Projects served by Northern Indiana Public Service Company

Related cases and proceedings

Sources

  1. 1
    NiSource release: IURC approval of the NIPSCO GenCo declination of jurisdiction (Cause No. 46183)
    NiSource Inc. (Business Wire)
    Tier 4 · NiSource release, 2025-09-24 (IURC approval of the GenCo declination petition; GenCo to own, build and manage generation for the data center industry in northern Indiana, protecting existing NIPSCO retail customers) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Verified Petition of NIPSCO Generation LLC for Certain Determinations by the Commission with Respect to Its Jurisdiction Over Petitioner's Activities as a Non-Retail Generator of Electric Power." Last activity 2025-09-24. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-nipsco-genco-46183