Utility commission
Verified Joint Petition of Northern Indiana Public Service Company LLC (NIPSCO) and NIPSCO Generation LLC (GenCo) for approval of a special contract (Data Center Customer #1 Special Contract), a power purchase agreement between NIPSCO and GenCo, and alternative regulatory plans
Where it stands: Decided as of Jun 17, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
15-year special contract with Amazon Data Services, Inc. (unnamed in the caption as Data Center Customer #1), approved with its settlement and the NIPSCO to GenCo power purchase agreement. Contracted deliveries begin January 1, 2027 and rise to 2,400 MW by the end of 2032, on an estimated $7 billion of investment to serve Amazon. The settling parties put the fixed cost contributions passed back to other retail customers at an estimated $1.1 billion over the 15-year term. March and May 2026 amendments that would raise the commitment to 2,800 MW were still awaiting IURC and FERC approval at the last reporting and are not rowed as approved.
The facts
- Regulator
- Indiana Utility Regulatory Commission
- Docket number
- Cause No. 46322
- Type
- Other
- Utility
- Northern Indiana Public Service Company
- State
- Indiana
- Filed
- Nov 7, 2025
- Status date
- Jun 17, 2026
- Large-load rules
- Yes
Projects served by Northern Indiana Public Service Company
Related cases and proceedings
- Utility commission · DecidedPetition of Indianapolis Power & Light Company d/b/a AES Indiana for approval of a project required primarily to serve a large load customer, customer-specific arrangements, and an alternative regulatory plan (Google, Morgan County)
- Utility commission · DecidedVerified Petition of NIPSCO Generation LLC for Certain Determinations by the Commission with Respect to Its Jurisdiction Over Petitioner's Activities as a Non-Retail Generator of Electric Power
- Utility commission · DecidedVerified Petition of Indiana Michigan Power Company for Approval of Modifications to Its Industrial Power Tariff, Tariff I.P.
- Court case · DecidedIndiana Michigan Power large load tariff settlement
- Court case · DecidedVerified Petition of Duke Energy Indiana, LLC for Approval of a Special Retail Electric Service Agreement, Renewable Energy Purchase Agreement, and Tranche Agreements with Blocke, LLC
- Utility commission · DecidedVerified Petition of Duke Energy Indiana, LLC for Approval of a Special Retail Electric Service Agreement, Renewable Energy Purchase Agreement, and Tranche Agreements with Blocke, LLC
In the record
- Utility case, Nov 7, 2025. Utility case filed: Verified Joint Petition of Northern Indiana Public Service Company LLC (NIPSCO) and NIPSCO Generation LLC (GenCo) for approval of a special contract (Data Center Customer #1 Special Contract), a power purchase agreement between NIPSCO and GenCo, and alternative regulatory plans Indiana Utility Regulatory Commission, Cause No. 46322
Sources
- 1Regulatory Approvals Underscore Strength of NiSource's Customer-Focused Data Center Strategy Supporting Growth in Indiana (NiSource release, republished)
NiSource Inc. (Business Wire, republished)Tier 4 · NiSource release, 2026-06-23, paragraphs 1-3 (June 17, 2026 full approval of the settlement, the Amazon special contract and the PPA; separate generation order the same day; about $1.4 billion in broader data center strategy savings) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Verified Joint Petition of Northern Indiana Public Service Company LLC (NIPSCO) and NIPSCO Generation LLC (GenCo) for approval of a special contract (Data Center Customer #1 Special Contract), a power purchase agreement between NIPSCO and GenCo, and alternative regulatory plans." Last activity 2026-06-17. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-nipsco-amazon-46322