Project File
Meta Eagle Mountain Data Center
Eagle Mountain,Utah County,UtahExpandingFirst public 2018Filing entity: Stadion LLCLast checked Nov 9, 2026
MetaDeveloper and operatorStadionDeveloperWill-Power UTOther role
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
6 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: Electric utility
- Confirmed: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Meta Eagle Mountain Data Center is an expanding data center project in Eagle Mountain, Utah County, Utah. Meta is named as operator. It was first public in 2018. No site capacity figure is published for this project.
Meta Eagle Mountain Data Center is an expanding data center project in Eagle Mountain, Utah County, Utah. Meta is named as operator. No site capacity figure is published for this project. All six of the core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Eagle Mountain, Utah County, Utah. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
- Property tax
The campus site had a $5,867 base taxable value in 2017; its assessed value passed $1.8 billion by tax year 2024.
Comes to the community - Tax breaks
Five taxing entities share the campus tax increment with the city redevelopment agency under agreements dating to 2018.
Comes from the community - Money for schools and services
Meta reports more than $6.2 million to local schools and organizations, and $4.85 million to the city's Affordable Housing Fund.
Comes to the community - Electricity bill
Meta's own index reports the campus used 1,115,619 megawatt-hours in 2024, up from 229,946 in 2021.
Comes from the community - Water
Eagle Mountain City supplies the campus water and sewer service under a May 25, 2018 agreement with Stadion LLC.
Comes from the community - Jobs
Meta says the expanded campus will support more than 300 operational jobs and 1,200 construction workers at peak.
Comes to the community - Next door: height, setbacks, noise
A 17-turbine gas plant is proposed at 247 North Pony Express Parkway to power a nearby data center.
Not known yet - Your say
The city council adopted the expansion development agreement on October 21, 2025, after a public meeting.
How to take part
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

The land, to scale
Timeline
- · FilingFiled with Meta Platforms, Inc. for Meta Eagle Mountain Data Center
- · FilingFiled with Utah Division of Air Quality: air permit for Meta Eagle Mountain Data CenterDAQE-NN163220001-26
- · FilingFiled with Eagle Mountain Redevelopment Agency for Meta Eagle Mountain Data Center
- · FilingFiled with Utah Public Service Commission for Meta Eagle Mountain Data Center25-2660-01
- · DecisionEagle Mountain City: Development Agreement between Eagle Mountain City and Stadion LLC covering approximately 541.4 acres of expansion property adjacent to the existing campus; adopted by City Council ordinance on October 21, 2025 after a public meeting (development agreement) for Meta Eagle Moun...
- · FilingFiled with Eagle Mountain City: development agreement for Meta Eagle Mountain Data Center
- · FilingFiled with Governor's Office of Economic Opportunity for Meta Eagle Mountain Data Center
- · New projectFirst public record of Meta Eagle Mountain Data CenterExpanding
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 507: Limits local incentives for large data centers outside development zones
The act covers large load data centers that are not located within a regionally significant development zone, for which a county or municipality may not offer an incentive, except project areas and agreements predating May 6, 2027; this project has 286 MW on record (generator capacity), but whether this project is a large load data center, whether it is located within such a zone, and whether a county or municipality offered it an incentive is not on record.
“Except as provided in Subsection (1)(b), a county or municipality may not offer an incentive for a large load data center that is not located within a zone.” (Utah Code Sec. 63N-3a-402(1)(a))
Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 76: Requires data centers to report water use before and after building
The act covers large data centers, facilities with an annual water withdrawal of 75 acre feet per year or more whose buildings total at least 10,000 square feet; this project has 286 MW on record (generator capacity), but the project's annual water withdrawal and its building area is not on record.
“"Large data center" means a facility with an annual water withdrawal of 75 acre feet per year or more that: (i) houses a group of networked server computers in one physical location to disseminate, manage, and store data and information as the primary service of the facility; (ii) consists of one or more buildings that in total equals or exceeds 10,000 square feet;” (Utah Code Sec. 73-5-8.3(1)(d), as enacted by H.B. 76, Section 2)
Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah SB 132: Sets cost and service rules for electric loads over 100 megawatts
The act covers large-scale service requests to a qualified electric utility, for new service expected to reach a cumulative demand of 100 megawatts or greater within five years, or added service expected to raise a customer's total by 100 megawatts or greater within five years; this project has 286 MW on record (generator capacity), but whether this project has submitted a large-scale service request and its expected demand within five years of the requested start date is not on record.
“"Large-scale service request" means a request submitted to a qualified electric utility for: (a) new electric service that is expected to reach a cumulative demand of 100 megawatts or greater within five years of the requested initial start date; or (b) additional electric service that is expected to increase a customer's total service level by 100 megawatts or greater within five years of the requested start date for the additional electric service.” (Definitions enacting Utah Code Title 54, Chapter 26, S.B. 132 enrolled text)
Rule checks: Project is in Utah. Still to check: size: unknown, dates: not checked, who it covers: not checked
Bills and laws in Utah
- HB 76 · In effect · May 6, 2026Requires data centers to report water use before and after building
- HB 507 · Signed into law · Mar 25, 2026Limits local incentives for large data centers outside development zones
- SB 132 · In effect · May 7, 2025Sets cost and service rules for electric loads over 100 megawatts
Who's involved
- Developer and operatorMeta
- DeveloperStadion
- Other roleWill-Power UT
Power and water
Water, as reported by the operator
Eagle Mountain (UT) facility as named in Meta's 2025 Environmental Data Index
- 2024 · Withdrawal: 133 ML
- 2023 · Withdrawal: 87 ML
- 2022 · Withdrawal: 89 ML
- 2021 · Withdrawal: 58 ML
Capacity, as announced or filed
- 286 MW · On-site generation plant (Project Aquila, Will-Power UT)Nov 2025 · generator_capacity
From the filings
Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.
Eagle Mountain Redevelopment Agency
- Stated in the filing
- $78.4 million
- Stated in the filing
- $778.5 million
- Stated in the filing
- $493.6 million
- Stated in the filing
- $46.9 million
- Stated in the filing
- $144.8 million
- Stated in the filing
- $14.9 million
Eagle Mountain City
- Stated in the filing
- 66:815:0001; 71:049:0001; 66:749:0002
- Stated in the filing
- 541.4 acres
Governor's Office of Economic Opportunity
- Stated in the filing
- 2021-01-01 to 2044-12-31
- Stated in the filing
- $5,867
- Stated in the filing
- $2.1 million
- Stated in the filing
- $14.3 million
- Stated in the filing
- $20 million
- Stated in the filing
- 100% of personal property tax increment and 80% of real and centrally assessed property tax increment
- Stated in the filing
- Buildings 5 and 6 completed in 2023 and on the tax rolls in TY 2024; two additional buildings completing summer 2025 for TY 2025
- Stated in the filing
- $935,382
- Stated in the filing
- $1.1 million
- Stated in the filing
- $4,000,000 per phase or $20,000,000 total, on real property tax only
- Stated in the filing
- $170 million
- Stated in the filing
- $1.85 billion
Eagle Mountain City
- Stated in the filing
- Eagle Mountain City provides water and sewer services to the project under a Water and Sewer Agreement with Stadion LLC dated May 25, 2018
Meta Platforms, Inc.
- Stated in the filing
- $50 million
- Stated in the filing
- $4.9 million
- Stated in the filing
- 300 jobs
- Stated in the filing
- $6.2 million
- Stated in the filing
- $3 billion
- Stated in the filing
- 1,200 workers
Utah Public Service Commission, 25-2660-01
- Stated in the filing
- Closed Private Generation System under Utah Code Section 54-26-504, co-located with the customer industrial property, with a 20-mile service pipeline
- Stated in the filing
- 286 MW
Utah Division of Air Quality, DAQE-NN163220001-26
- Stated in the filing
- none
- Stated in the filing
- 17 units
- Stated in the filing
- 247 North Pony Express Parkway, Eagle Mountain, UT 84005
- Stated in the filing
- 8 units
- Stated in the filing
- 2 units
Public records
21 records found so far. 4 kinds of record are still being collected.
- Land and zoning rules2
- Environmental permits1
- Power and utility13
- Tax breaks and payments2
- Votes and minutes3
Court cases and commission dockets
- Utility commission · Pending before the commission · Sep 16, 2026PacifiCorp Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities
- Utility commission · Pending before the commission · Aug 19, 2026Amazon Data Services, Inc. v. PacifiCorp d/b/a Pacific Power
- Utility commission · Pending before the commission · Apr 28, 2026Division of Public Utilities' Request for an Investigatory Docket Regarding Rocky Mountain Power's Line Extension Policy for Large Loads
- Utility commission · Decided · Mar 19, 2026Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
- Utility commission · In effect · Jan 1, 2026Proposed Rulemaking Concerning Utah Code Sections 54-26-101 to -901, Large-Scale Electric Service Requirements
- Utility commission · In effect · Jan 1, 2026Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
- Utility commission · In effect · Jun 1, 2025Rocky Mountain Power Electric Service Schedule No. 400, Special Contracts (Wyoming)
- Utility commission · In effect · Feb 1, 2025Rocky Mountain Power Electric Service Schedule No. 400, Special Contract (Idaho)
Questions people ask
- Where is Meta Eagle Mountain Data Center?
- Meta Eagle Mountain Data Center is a data center project in Eagle Mountain, Utah County, Utah.
- Who operates Meta Eagle Mountain Data Center?
- Meta is named as the operator of Meta Eagle Mountain Data Center.
- How big is Meta Eagle Mountain Data Center?
- The site covers 471.48 acres.
- What stage is Meta Eagle Mountain Data Center?
- Meta Eagle Mountain Data Center is expanding. It was first public in 2018.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Notice of Hearing, Sweetwater Industrial Park Community Reinvestment Project Area #4, amended plan and budget (posted December 5, 2025)
Eagle Mountain Redevelopment Agency (via Utah Public Meeting Notice)Tier 1 · Captured 2026-11-09 · Open the source - 2Development Agreement between Eagle Mountain City and Stadion LLC (expansion property), adopted October 21, 2025
City of Eagle Mountain (via Utah Public Meeting Notice)Tier 1 · Captured 2026-11-09 · Open the source - 3RDA Project Area Yearly Report: 2025 - Sweet Water #1 CRA
Utah Governor's Office of Economic Opportunity (GOED RDA reporting system)Tier 1 · Captured 2026-11-09 · Open the source - 4RDA Yearly Report Taxing Entity: 2025 - UNIFIED FIRE SERVICE - Sweet Water #1 CRA
Utah Governor's Office of Economic Opportunity (GOED RDA reporting system)Tier 1 · Captured 2026-11-09 · Open the source - 5RDA Yearly Report Taxing Entity: 2025 - UTAH CNTY - Sweet Water #1 CRA
Utah Governor's Office of Economic Opportunity (GOED RDA reporting system)Tier 1 · Captured 2026-11-09 · Open the source - 6RDA Yearly Report Taxing Entity: 2025 - EAGLE MT - Sweet Water #1 CRA (taxing entity not named in the rendered record)
Utah Governor's Office of Economic Opportunity (GOED RDA reporting system)Tier 1 · Captured 2026-11-09 · Open the source - 7Deepening Our Investment in Eagle Mountain, Utah
Meta Platforms, Inc.Tier 4 · Captured 2026-11-09 · Open the source - 8Notice of Registration of Will-Power UT, LLC as a Large-Scale Generation Provider, Docket No. 25-2660-01
Utah Public Service CommissionTier 1 · Captured 2026-11-08 · Open the source - 9Legal Notice of Intent to Approve DAQE-NN163220001-26: Will-Power UT, LLC - Eagle Mountain Power Generation Facility
Utah Division of Air QualityTier 1 · Captured 2026-11-08 · Open the source - 10Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
PacifiCorp d/b/a Pacific Power & Light CompanyTier 1 · Captured 2026-11-08 · Open the source - 11Settlement Stipulation, Docket No. 26-035-05, Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
Public Service Commission of Utah (filing by Rocky Mountain Power with the Division of Public Utilities and the Office of Consumer Services)Tier 1 · Captured 2026-11-08 · Open the source - 12Notice of Decisions on UAE motion and approval of the Settlement Stipulation, Docket No. 26-035-05
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 13Rocky Mountain Power advances Utah's Operation Gigawatt through landmark energy agreement
Rocky Mountain Power (PacifiCorp)Tier 4 · Captured 2026-11-08 · Open the source - 14Notice of Comment Period, Docket Nos. 25-R318-01 and 24-035-43 (large load flexible tariff guidance; R746-318 New Rule)
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 15Rocky Mountain Power Idaho Electric Service Schedule No. 400, Special Contract (I.P.U.C. No. 1, Thirteenth Revision of Sheet No. 400.1)
Rocky Mountain Power (PacifiCorp)Tier 1 · Captured 2026-11-08 · Open the source - 16Final Order No. 35277, Case No. PAC-E-21-07 (Rocky Mountain Power Idaho rate case)
Idaho Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 17Order No. 23-472, PacifiCorp Revision of Rule 13 Line Extension Policy, Docket UE 424
Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 18Rocky Mountain Power Wyoming Electric Service Schedule No. 400, Special Contracts (P.S.C. Wyoming No. 19, Original Sheets 400-1 to 400-3)
Rocky Mountain Power (PacifiCorp)Tier 1 · Captured 2026-11-08 · Open the source - 19Public notice of Rocky Mountain Power application to establish Tariff Schedule 400, Special Contracts, Docket No. 20000-602-ET-21 (legal notice as published July 13, 2021)
Wyoming Public Service Commission (notice published in the Kemmerer Gazette)Tier 1 · Captured 2026-11-08 · Open the source - 20PacifiCorp Reply Testimony of Craig M. Eller, Oregon Docket No. UE 463, Exhibit PAC/200
PacifiCorpTier 1 · Captured 2026-11-08 · Open the source - 21Memorandum to service list in Docket No. 25-R318-01 with Charles River Associates clarification and guidance on the initial SB 132 rules
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 22Utah Code Title 54, Chapter 26, Part 1, General Provisions (Large-Scale Electric Service Requirements), effective May 7, 2025
Utah State LegislatureTier 1 · Captured 2026-11-08 · Open the source - 23Utah Code Section 54-26-301, Large load contract requirements, effective May 7, 2025
Utah State LegislatureTier 1 · Captured 2026-11-08 · Open the source - 24PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 25Staff Opening Testimony (Staff/100), Docket UE 463
Staff of the Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 26Data Center Coalition Opening Testimony of Bieber, Docket UE 463
Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)Tier 1 · Captured 2026-11-08 · Open the source - 27Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
Staff of the Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 28Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
PacifiCorp d/b/a Pacific PowerTier 1 · Captured 2026-11-08 · Open the source - 29UTC Case Docket Detail Page, Docket UE-231037 (PacifiCorp, Advice 23-06)
Washington Utilities and Transportation CommissionTier 1 · Captured 2026-11-08 · Open the source - 30PacifiCorp Advice 23-06 cover letter and Rule 14 tariff sheets, Docket UE-231037
PacifiCorp d/b/a Pacific Power & Light Company (filed with the Washington Utilities and Transportation Commission)Tier 1 · Captured 2026-11-08 · Open the source - 31Alliance of Western Energy Consumers filing in Docket No. UE 463
Public Utility Commission of OregonTier 1 · Captured 2026-11-07 · Open the source - 32PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
Public Utility Commission of OregonTier 1 · Captured 2026-11-07 · Open the source - 33Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source - 34ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 35Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source - 36Facebook building Eagle Mountain City, UT data center (joint Eagle Mountain City, Utah GOED, and EDCUtah announcement, 2018-05-30, republished)
Eagle Mountain City / Utah GOED / EDCUtahTier 1 · Captured 2026-11-08 · Open the source - 37United States - Meta Data Centers (fleet list incl. Fort Worth)
MetaTier 4 · Captured 2026-11-08 · Open the source - 38Utah County GIS parcel layer (Parcel_TaxParcels_Simple_wgs84), queried 2026-11-09
Utah County GISTier 1 · Captured 2026-11-09 · Open the source - 39Meta 2025 Environmental Data Index
Meta Platforms, Inc.Tier 4 · Captured 2026-11-08 · Open the source