Data centers in Mecklenburg County, Virginia

Last checked Nov 7, 2026

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 10 data center projects in Mecklenburg County, Virginia as of November 2026: 8 stage not known, 1 under construction and 1 operating, totaling about 300 MW announced where a figure is published.

Mecklenburg County has 10 tracked data centers. Together they paid $22.7 million in property tax in FY 2025, 31.4 percent of fy2025. Of those, 1 under construction and 1 operating; the stage of the other 8 is not known yet. Every figure comes from the public record linked on this page.

10Data center projects we track
31.4 percentof fy2025 comes from data centers (the county's figure, FY 2025)
$22.7 millionProperty tax paid by data centers, FY 2025
0.31Real property tax rate, USD per 100 USD of assessed value, FY 2027

Data center projects in Mecklenburg County

Who serves this place

  • ElectricityDominion Energy Virginia
  • ElectricityMecklenburg Electric Cooperative
  • ElectricitySouthside Electric Cooperative
  • WaterRoanoke River Service Authority
  • WaterTown of Boydton
  • Grid regionPJM

Places in and around Mecklenburg County

Mecklenburg County is part of Virginia.

Cities and towns

Nearby places

For homeowners

What the projects here mean if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

  2. Tax breaks

    • Microsoft data center campus (Boydton):The county reported $57,719,970 abated in fiscal 2023 across two unnamed entities; Virginia also exempts qualifying data center equipment from state sales tax.

      Goes both ways
  3. Money for schools and services

  4. Electricity bill

  5. Water

  6. Jobs

  7. Next door: height, setbacks, noise

  8. Your say

Taxes and budget over time

As published by the county, not adjusted for inflation. Projections are labeled.

Property tax paid by data centers

Property tax paid by data centers by year
FY 2025$22.7 million

Total property tax revenue

Total property tax revenue by year
FY 2025$72.2 million
FY 2023$110.7 million
FY 2022$98.7 million

Real property tax rate

Real property tax rate by year
FY 20270.31 USD per 100 USD of assessed value
FY 20260.36 USD per 100 USD of assessed value
FY 2025Projection0.37 USD per 100 USD of assessed value
FY 20240.4 USD per 100 USD of assessed value

Personal property tax rate

Personal property tax rate by year
FY 20270.66 USD per 100 USD of assessed value
FY 20273.26 USD per 100 USD of assessed value
FY 20260.66 USD per 100 USD of assessed value
FY 20263.26 USD per 100 USD of assessed value

Total assessed value

Total assessed value by year
FY 2025$7.97 billion

General fund budget

General fund budget by year
FY 2027$133.8 million
FY 2025Projection$89.7 million

Tax breaks and payments

  • 2010 · Microsoft data center campus (Boydton)

    Economic stimulus grants (rebates of taxes paid)

    A grant of 90 percent of the company's personal property tax for 20 years, plus a grant of 100 percent of the county machinery and tools tax for 5 years.

    All tax records for Microsoft data center campus (Boydton)
  • Property tax abatement agreements (individually negotiated by the County and its Industrial Development Authority)

    82.5 percent of taxes abated across machinery and tools tax, real estate tax, and business personal property tax; stated purpose is to increase size and employment in the Southside Virginia area.

Local rules for data centers

  • In effect · Noise · Adopted May 11, 2026

    Data center noise limit of 70 dBA at the property line, with sound studies on demand

    Noise from all activities at a data center development may not exceed 70 dBA measured at the property line shared with non data center uses. The limit does not apply to demolition work, to sudden unforeseen events that require emergency vehicles or temporary emergency generator use, or to generator testing inside the allowed testing window. The Zoning Administrator may require a sound study at any time, due within 15 days and taken during peak cooling operations, and the operator must act at once to comply if the study shows an exceedance.

  • In effect · Zoning · Adopted May 11, 2026

    Data center is a special exception use, not a by right use

    In the county use table, Data center is listed as SE, meaning a special exception permit is required, in two district columns, and the supplemental standards at Section 7.1-7 are written around that special exception process. Data center does not appear as a permitted by right use in the table rows read. The table text extraction jumbles column order, so the two districts carrying the SE marking are not named here; the M-1 Industrial district is the district applied to the Boydton campus area.

  • In effect · Other · Adopted May 11, 2026

    Extra application studies for data centers that are high energy use facilities

    A data center that qualifies as a high energy use facility must add two items to its special exception application: an acoustical site assessment covering homes and schools within 500 feet of the property line, and a formal statement from the electric utility on substations and transmission voltage needed to serve the site. County staff may also require a site impact assessment covering water use and water sources, prime farmland, forest cover loss, and visibility from parks and historic sites within a half mile.

  • In effect · Other · Adopted May 11, 2026

    Data center buffers, fencing, and equipment screening standards

    Data center sites must be buffered from public roadways and from natural and managed resource areas such as parks, wildlife areas, forestland, and timberland, using at least a Buffer Type A planting, with walls, fences, or berms allowed only as a supplement to landscaping. Chain link fencing visible from a street is prohibited, barbed wire and razor wire may not be visible from the public right of way or nearby homes, and electrical substations and mechanical equipment must be screened under the landscaping and screening section.

  • In effect · Generator · Adopted May 11, 2026

    Generator testing window and sound attenuating enclosures for data centers

    Generator testing at a data center is covered by the 70 dBA property line limit only when it runs between 10:00 a.m. and 4:00 p.m., unless the Department of Environmental Quality requires testing outside that window. All generators must be housed in sound attenuating enclosures or use other sound mitigation the Zoning Administrator approves.

In the news

More stories about this place

Court cases and commission dockets in Virginia (15)

Bills and laws in Virginia

All 29 in Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in Mecklenburg County?
Data Center Fact Check tracks 10 data center projects in Mecklenburg County as of November 2026. Of those, 1 under construction and 1 operating; the stage of the other 8 is not known yet.
What is the biggest data center in Mecklenburg County?
By announced capacity, the biggest data center in Mecklenburg County is TECfusions Clarksville, announced at 300 MW. It is under construction.
How much power do data centers in Mecklenburg County use?
The 10 projects tracked in Mecklenburg County have announced about 300 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
How much property tax do data centers pay in Mecklenburg County?
Data centers paid $22.7 million in property tax in FY 2025. Data centers account for 31.4 percent of fy2025.

Sources

  1. 1
    FY 2025 Annual Comprehensive Financial Report
    Mecklenburg County, Virginia
    Tier 1 · Open the source
  2. 2
    Board of Supervisors minutes, May 11, 2026
    Mecklenburg County, Virginia
    Tier 1 · Open the source
  3. 3
    Annual Drinking Water Quality Report, 2025 Consumer Confidence Report, Town of Boydton (PWSID 5117100)
    Town of Boydton
    Tier 1 · Open the source
  4. 4
    Dominion Supplemental Projects, Transmission Expansion Advisory Committee, May 6, 2025
    PJM Interconnection
    Tier 1 · Open the source
  5. 5
    Mecklenburg County and EMPOWER VATI application to the Virginia Department of Housing and Community Development
    Mecklenburg County and Mecklenburg Electric Cooperative
    Tier 1 · Open the source
  6. 6
    Tell me more about SEC
    Southside Electric Cooperative
    Tier 1 · Open the source
  7. 7
    Data centers in Mecklenburg County, electric utilities section
    Data Centers Near You
    Tier 3 · Open the source
  8. 8
    FY 2025 Recommended Budget
    Mecklenburg County, Virginia
    Tier 1 · Open the source
  9. 9
    Board of Supervisors minutes, May 12, 2025
    Mecklenburg County, Virginia
    Tier 1 · Open the source
  10. 10
    Board of Supervisors minutes, April 13, 2026
    Mecklenburg County, Virginia
    Tier 1 · Open the source
  11. 11
    County lines up incentive package, The Mecklenburg Sun, July 14, 2010
    The Mecklenburg Sun (SoVaNow)
    Tier 3 · Open the source
  12. 12
    Annual Comprehensive Financial Report, Year Ended June 30, 2023
    County of Mecklenburg, Virginia
    Tier 1 · Open the source
  13. 13
    Code of Virginia, Section 58.1-609.3, subdivision 18 (data center sales and use tax exemption)
    Virginia Legislative Information System
    Tier 1 · Open the source
  14. 14
    Data Center Retail Sales & Use Tax Exemption
    Virginia Economic Development Partnership
    Tier 1 · Open the source
  15. 15
    EIA Form 861 2025, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Open the source
  16. 16
    EIA Form 861 2016, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Open the source
  17. 17
    Virginia, EDA FY 2015 Annual Report
    U.S. Economic Development Administration
    Tier 1 · Open the source
  18. 18
    Initial Title V Permit, Microsoft Corp, East Coast Data Center (Permit No. PRO-21527)
    Virginia Department of Environmental Quality
    Tier 1 · Open the source
  19. 19
    Stationary Source Permit to Construct and Operate, significant amendment (permit action 21527-15), Microsoft Corporation, East Coast Data Center
    Virginia Department of Environmental Quality
    Tier 1 · Open the source
  20. 20
    Board of Supervisors Minutes, August 10, 2020
    Mecklenburg County
    Tier 1 · Open the source
  21. 21
    Mecklenburg County Planning Commission agenda packet, March 19, 2026 (includes Zoning Ordinance Draft 3-3-2026)
    Mecklenburg County, Virginia
    Tier 1 · Open the source
  22. 22
    Mecklenburg County rezones near Microsoft site
    SoVaNOW (The News & Record and The Mecklenburg Sun)
    Tier 3 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Mecklenburg County." Last checked 2026-11-07. Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-va-mecklenburg

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page