Data centers in Ector County, Texas
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 2 data center projects in Ector County, Texas as of November 2026: 1 announced and 1 operating, totaling about 1,207 MW announced where a figure is published.
Ector County has 2 tracked data centers. Their announced capacity totals about 1,207 MW where a figure is published. Of those, 1 announced and 1 operating. The projects here are Cipher Odessa and Texas Critical Data Centers (TCDC). Every figure comes from the public record linked on this page.
Data center projects in Ector County
- Cipher Odessa
OperatingOdessa207 MW announced
- Texas Critical Data Centers (TCDC)
AnnouncedOdessa1,000 MW announced
Who serves this place
- Not collected yet.
A data center is proposed in Ector County
1 project here is at the announced or proposed stage. Before the hearing, the resident checklist walks through what to check: the proposal's documents, the local rules where you live, the tax agreement, and the recorded votes.
Places in and around Ector County
Ector County is part of Texas.
Cities and towns
- Odessa2 data center projects tracked
Nearby places
- Dallas County36 data center projects tracked
- Bexar County16 data center projects tracked
- Collin County10 data center projects tracked
- Harris County9 data center projects tracked
- Denton County7 data center projects tracked
- Ellis County7 data center projects tracked
- Medina County6 data center projects tracked
- Tarrant County6 data center projects tracked
- Haskell County3 data center projects tracked
- Pecos County3 data center projects tracked
- Reeves County3 data center projects tracked
- Williamson County3 data center projects tracked
Court cases and commission dockets in Texas (18)
Bills and laws in Texas
- SB 6 · Signed into law · Jun 20, 2025Sets grid connection and cost rules for large loads in Texas
- SB 2222 · Died or failed · Mar 25, 2025Would exempt data center property and energy equipment from property tax
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Ector County?
- Data Center Fact Check tracks 2 data center projects in Ector County as of November 2026. Of those, 1 announced and 1 operating.
- What is the biggest data center in Ector County?
- By announced capacity, the biggest data center in Ector County is Texas Critical Data Centers (TCDC), announced at 1,000 MW. It is announced.
- How much power do data centers in Ector County use?
- The 2 projects tracked in Ector County have announced about 1,207 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Ector County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-tx-ector