Data Center Fact Check tracks 3 data center projects in Pecos County, Texas as of November 2026: 2 stage not known and 1 operating, totaling about 25 MW announced where a figure is published.
Pecos County has 3 tracked data centers. Their announced capacity totals about 25 MW where a figure is published. Of those, 1 operating; the stage of the other 2 is not known yet. Every figure comes from the public record linked on this page.
Data center projects in Pecos County
- Lancium Fort Stockton Clean Campus
Operating25 MW announced
- Poolside Data Center, Pecos County I
Stage not known
- Poolside Data Center, Pecos County II
Stage not known
Who serves this place
- Not collected yet.
Places in and around Pecos County
Pecos County is part of Texas.
Nearby places
- Dallas County36 data center projects tracked
- Bexar County16 data center projects tracked
- Collin County10 data center projects tracked
- Harris County9 data center projects tracked
- Denton County7 data center projects tracked
- Ellis County7 data center projects tracked
- Medina County6 data center projects tracked
- Tarrant County6 data center projects tracked
- Haskell County3 data center projects tracked
- Reeves County3 data center projects tracked
- Williamson County3 data center projects tracked
- Bosque County2 data center projects tracked
Tax breaks and payments
Economic development agreement (Texas Local Government Code Chapter 380)
Economic development agreement (abatement); amendment reports total agreement amount $595,000
Economic development agreement (Texas Local Government Code Chapter 380)
20-year partial tax abatement (as described in the filing)
Court cases and commission dockets in Texas (18)
Bills and laws in Texas
- SB 6 · Signed into law · Jun 20, 2025Sets grid connection and cost rules for large loads in Texas
- SB 2222 · Died or failed · Mar 25, 2025Would exempt data center property and energy equipment from property tax
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Pecos County?
- Data Center Fact Check tracks 3 data center projects in Pecos County as of November 2026. Of those, 1 operating; the stage of the other 2 is not known yet.
- What is the biggest data center in Pecos County?
- By announced capacity, the biggest data center in Pecos County is Lancium Fort Stockton Clean Campus, announced at 25 MW. It is operating.
- How much power do data centers in Pecos County use?
- The 3 projects tracked in Pecos County have announced about 25 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Local Development Agreement Database (SB 1340), Chapter 380/381 agreements dataset
Texas Comptroller of Public AccountsTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Pecos County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-tx-pecos
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page