County Card
Data centers in Buffalo County, Nebraska
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 3 data center projects in Buffalo County, Nebraska as of November 2026: 2 approved and 1 operating, totaling about 473 MW announced where a figure is published.
Buffalo County has 3 tracked data centers. Their announced capacity totals about 473 MW where a figure is published. Of those, 2 approved and 1 operating. The projects here are MARA Kearney mining facility, Project Horizon (Tech oNE Crossing), and Sequitor Edge Kearney data center. Every figure comes from the public record linked on this page.
Data center projects in Buffalo County
- MARA Kearney mining facility
OperatingKearney100 MW announced
- Project Horizon (Tech oNE Crossing)
ApprovedKearney368 MW announced
- Sequitor Edge Kearney data center
ApprovedKearney5 MW announced
Who serves this place
- Not collected yet.
Places in and around Buffalo County
Buffalo County is part of Nebraska.
Cities and towns
- Kearney3 data center projects tracked
Nearby places
- Sarpy County9 data center projects tracked
- Douglas County4 data center projects tracked
- Lancaster County4 data center projects tracked
- Hall County3 data center projects tracked
- Lincoln County2 data center projects tracked
- Stanton County2 data center projects tracked
- Cass County1 data center project tracked
- Kearney County1 data center project tracked
Bills and laws in Nebraska
- EO 26-17 · In effect · Jul 21, 2026Ends ImagiNE Act tax incentives for new data centers and creates a data center task force
- LB 1064 · Died or failed · Apr 17, 2026Interconnection standards for large load customers
- LB 1111 · Died or failed · Apr 17, 2026Annual reporting and full cost rates for large data centers
- LB 1131 · Died or failed · Apr 17, 2026Ends data center tax exemptions to fund victim services credits
- LB 1010 · Signed into law · Apr 14, 2026Sets connection standards and reporting for large load customers
- LB 1261 · Signed into law · Apr 14, 2026Lets very large loads build their own power plants that public power cannot take by eminent domain
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Buffalo County?
- Data Center Fact Check tracks 3 data center projects in Buffalo County as of November 2026. Of those, 2 approved and 1 operating.
- What is the biggest data center in Buffalo County?
- By announced capacity, the biggest data center in Buffalo County is Project Horizon (Tech oNE Crossing), announced at 368 MW. It is approved.
- How much power do data centers in Buffalo County use?
- The 3 projects tracked in Buffalo County have announced about 473 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Buffalo County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ne-buffalo
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page