NebraskaUnicameral Legislature109th Legislature, 2nd Session (2026)Bill
LB 1261: Lets very large loads build their own power plants that public power cannot take by eminent domain
Official title: Prohibit the use of eminent domain to acquire certain privately owned electric generation facilities
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Signed into law as of Apr 14, 2026. The official record says: Approved by Governor on April 14, 2026.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (done)
- Signed into law (current stage)
- In effect (not reached)
What it does
We have not quoted its provisions yet. The official text has them.
Who it touches
No project we track is matched to this bill or order: its rules do not reach them, or a check found it does not apply.
Other projects we track in Nebraska (29), not affected
- 1623 Farnam data centerOperating
- ArchGreen Doniphan data center (permit denied)Cancelled
- ArchGreen Grand Island data center (Project 1)Operating
- CLOP Omaha NE data centerIn permitting
- Coffee Grounds Data (Arevia Power) Malcolm siteProposed
- Cogent OmahaOperating
- Fidelity Investments Papillion data centerOperating
- Fortitude Mining Grand Island data centerOperating
- Google Lincoln data centerOperating
- Google Northwest Omaha data centerOperating
- Google Papillion data centerOperating
- Hershey area data center (developer not named in public records)Proposed
- Jigowatt Stanton County mining facilityOperating
- LightEdge Omaha data centerOperating
- MARA Kearney mining facilityOperating
- MARA Minden mining facilityOperating
- Meta Sarpy County Data CenterExpanding
- Monolith and Crusoe Hallam data centerApproved
- Northern Data Stanton County cloud hub (not built)Cancelled
- Pinpoint North Platte data centerOperating
- Project Horizon (Tech oNE Crossing)Approved
- Sagebrush and Stark Power Hallam campusProposed
- Scott Data CenterOperating
- Sequitor Edge Kearney data centerApproved
- Tenaska and Google southeast Nebraska data center and power campusProposed
- TierPoint Omaha - Bellevue data centerOperating
- TierPoint Omaha - Midlands data centerOperating
- Travelers Sarpy CountyOperating
- Yahoo La Vista data center campus (H5 Omaha)Operating
Who acted
- SponsorSen. Barry DeKay (at the request of the Governor)
More from Nebraska
- LB 1131 · Died or failedEnds data center tax exemptions to fund victim services credits
- LB 1064 · Died or failedInterconnection standards for large load customers
- LB 1111 · Died or failedAnnual reporting and full cost rates for large data centers
- LB 1010 · Signed into lawSets connection standards and reporting for large load customers
Sources
- 1LB1261, Prohibit the use of eminent domain to acquire certain privately owned electric generation facilities (bill page with history)
Nebraska Legislature (nebraskalegislature.gov)Tier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.