Sequitor Edge Kearney data center
Kearney,Buffalo County,NebraskaApprovedFirst public 2025Filing entity: Sequitor America, LLCLast checked Nov 8, 2026
Sequitor EdgeDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Sequitor Edge Kearney data center is an approved data center project in Kearney, Buffalo County, Nebraska. Sequitor Edge is named as operator. It was first public in 2025. It was announced at 5 MW.
Sequitor Edge Kearney data center is an approved data center project in Kearney, Buffalo County, Nebraska. Sequitor Edge is named as operator. It was announced at 5 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Kearney, Buffalo County, Nebraska. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Sequitor Edge Kearney data centerApproved
Bills and laws in Nebraska
- EO 26-17 · In effect · Jul 21, 2026Ends ImagiNE Act tax incentives for new data centers and creates a data center task force
- LB 1064 · Died or failed · Apr 17, 2026Interconnection standards for large load customers
- LB 1111 · Died or failed · Apr 17, 2026Annual reporting and full cost rates for large data centers
- LB 1131 · Died or failed · Apr 17, 2026Ends data center tax exemptions to fund victim services credits
- LB 1010 · Signed into law · Apr 14, 2026Sets connection standards and reporting for large load customers
- LB 1261 · Signed into law · Apr 14, 2026Lets very large loads build their own power plants that public power cannot take by eminent domain
Who's involved
- Developer and operatorSequitor Edge
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Sequitor Edge Kearney data center?
- Sequitor Edge Kearney data center is a data center project in Kearney, Buffalo County, Nebraska.
- Who operates Sequitor Edge Kearney data center?
- Sequitor Edge is named as the operator of Sequitor Edge Kearney data center.
- How big is Sequitor Edge Kearney data center?
- Sequitor Edge Kearney data center was announced at 5 MW of capacity. The site covers 16 acres.
- What stage is Sequitor Edge Kearney data center?
- Sequitor Edge Kearney data center is approved. It was first public in 2025.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Kearney City Council minutes, August 25, 2026
City of KearneyTier 1 · Captured 2026-11-08 · Open the source - 2Sequitor Edge to build data center on 16-acre land parcel in Kearney, Nebraska
Data Center DynamicsTier 3 · Captured 2026-11-08 · Open the source - 3Citizen raises concerns about potential data center impact to Kearney
KRNY (KearneyHub / Nebraska radio)Tier 3 · Captured 2026-11-08 · Open the source