Data center court cases and dockets in Oregon
A docket is a case's public file. These are the lawsuits and the utility commission proceedings (rate cases, large-load rules, agreements) that touch data centers, newest activity first. Each links to its source.
11 dockets
Cases and proceedings
Utility commissionPending before the commissionLarge loads
PacifiCorp Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities
Public Utility Commission of Oregon · Docket UE 463 · PacifiCorp · Oregon
Utility commissionPending before the commissionLarge loads
Amazon Data Services, Inc. v. PacifiCorp d/b/a Pacific Power
Public Utility Commission of Oregon · Docket UM 2410 · PacifiCorp · Oregon
Utility commissionIn effectLarge loads
Investigation into Marginal Cost Study Treatment of Costs for Large Customers and Further Modifications to Portland General Electric Company's Rule C and Rule I
Public Utility Commission of Oregon · Docket UM 2377 · Portland General Electric Co · Oregon
Court casePending
1000 Friends of Oregon et al. v. City of Hillsboro et al.
Circuit Court of the State of Oregon for the County of Washington · Docket 26CV30954 · Washington County · Oregon
About: NTT Hillsboro data center campus
Utility commissionIn effectLarge loads
Special large customer rate class and Facility Site Evaluation Request process
Board of Directors, Northern Wasco County People's Utility District · Northern Wasco County PUD · Oregon
Utility commissionIn effectLarge loads
Investigation into New Load Connection Costs (Advice No. 24-38, revisions to Rule C and Rule I)
Public Utility Commission of Oregon · Docket UE 430 · Portland General Electric Co · Oregon
Utility commissionIn effectLarge loads
Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
Public Utility Commission of Oregon · PacifiCorp · Oregon
Utility commissionDecidedLarge loads
PacifiCorp Request for a General Rate Revision (2024 general rate case, very large customer charges)
Public Utility Commission of Oregon · Docket UE 433 · PacifiCorp · Oregon
Utility commissionIn effectLarge loads
PacifiCorp Advice No. 23-016, Revision of Oregon Rule 13 Line Extension Policy
Public Utility Commission of Oregon · Docket UE 424 · PacifiCorp · Oregon
Utility commissionDecidedLarge loads
Joint petition of PGE and QTS Investment Properties Hillsboro, LLC to increase Green Tariff Customer Supply Option capacity (GEAR, Schedule 55)
Public Utility Commission of Oregon · Docket UM 2202 · Portland General Electric Co · Oregon
Court caseSettled
City of The Dalles v. The Oregonian (Google water records)
Wasco County Circuit Court (Oregon) · Docket 21CV40820 · Wasco County · Oregon
About: Google The Dalles data center campus
Sources on this page
- 1Alliance of Western Energy Consumers filing in Docket No. UE 463
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 2PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 3Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 4ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 5Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 6Order No. 26-154, Investigation into Marginal Cost Study Treatment of Costs for Large Customers and Further Modifications to Portland General Electric Company's Rule C and Rule I, Docket UM 2377
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 7Oregon PUC Approves New Rate Structure to Protect Customers Amid Rapid Data Center Growth
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 8Petition for Writ of Review and Complaint for Declaratory and Injunctive Relief, 1000 Friends of Oregon et al. v. City of Hillsboro et al., Case No. 26CV30954 (filed 2026-06-22)
Circuit Court of the State of Oregon for the County of WashingtonTier 1 · Draft research, not yet verified · Open the source - 9Northern Wasco County PUD presentation to the Governor's Data Center Advisory Committee
Northern Wasco County People's Utility DistrictTier 1 · Draft research, not yet verified · Open the source - 10Preparing for the Future: Northern Wasco County PUD's Commitment to Smart and Equitable Growth
Northern Wasco County People's Utility DistrictTier 1 · Draft research, not yet verified · Open the source - 11Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
Staff of the Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 12Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
PacifiCorp d/b/a Pacific PowerTier 1 · Draft research, not yet verified · Open the source - 13PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 14Staff Opening Testimony (Staff/100), Docket UE 463
Staff of the Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 15Data Center Coalition Opening Testimony of Bieber, Docket UE 463
Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)Tier 1 · Draft research, not yet verified · Open the source - 16Order No. 23-472, PacifiCorp Revision of Rule 13 Line Extension Policy, Docket UE 424
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 17Joint Petition of Portland General Electric Company and QTS Investment Properties Hillsboro, LLC to Increase Green Tariff Customer Supply Option Capacity (UM 2202)
Public Utility Commission of Oregon (joint filing of Portland General Electric Company and QTS Investment Properties Hillsboro, LLC)Tier 1 · Draft research, not yet verified · Open the source - 18Order No. 21-468, UM 2202 (entered December 20, 2021)
Public Utility Commission of OregonTier 1 · Draft research, not yet verified · Open the source - 19Good day for journalism: The Dalles, Google abdicate in water fight with Oregonian
Columbia InsightTier 3 · Draft research, not yet verified · Open the source - 20Total City and Google Water Consumption (gal.), current as of January 21, 2026
City of The DallesTier 1 · Draft research, not yet verified · Open the source