Utility commission
Application of Ohio Power Company for approval of a Data Center Power tariff (Schedule DCT) and a Mobile Data Center tariff
Where it stands: Decided as of Jul 9, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
Schedule DCT covers new data center customers at 25 MW or more monthly maximum demand at a single location; a separate Mobile Data Center schedule covers mobile data centers (for example cryptocurrency miners) at 1 MW or more. Minimum billing demand is 85 percent of contract demand at full ramp (the adopted schedule applies a size-based formula that reaches 85 percent for the largest customers), over a term of up to 12 years including a four-year ramp-up. Customers must post collateral or other financial assurance and pay an exit fee on early termination. Existing data centers are grandfathered unless they expand past 25 MW. The Commission adopted the October 23, 2024 joint stipulation as modified; rehearing was denied September 3, 2025, and compliance tariffs took effect July 23, 2025.
The facts
- Regulator
- Public Utilities Commission of Ohio
- Docket number
- 24-508-EL-ATA
- Type
- Large load tariff
- Utility
- AEP Ohio
- State
- Ohio
- Filed
- May 13, 2024
- Status date
- Jul 9, 2025
- Large-load rules
- Yes, for loads of 25 MW or more
Projects served by AEP Ohio
- Amazon Web Services Hilliard campus
- Amazon Web Services New Albany campus (2015)
- Amazon Web Services New Albany expansion (2023)
- Cologix COL5 (Columbus)
- Expedient Upper Arlington
- Google Lima data center
- Google New Albany data center
- Meta New Albany Data Center
- QTS New Albany 1 campus
- QTS New Albany 2 campus
- QTS Van Wert (Van Wert; listed as in development)
Related cases and proceedings
- Utility commission · Pending before the commissionApplication of Duke Energy Ohio for approval of a data center rate class (Rate DC)
- Utility commission · Pending before the commissionApplication of The Dayton Power and Light Company (AES Ohio) for an increase in electric distribution rates, multi-year rate plan 2027-2029, with a stipulated Data Center Tariff
- Court case · PendingCity of Hilliard v. Ohio Environmental Protection Agency (fuel cell permit appeal)
- Utility commission · Pending before the commissionJoint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
- Utility commission · Pending before the commissionJoint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
- Utility commission · Pending before the commissionJoint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
- Court case · DecidedState ex rel. Bristolville 25 Developer, L.L.C., et al. v. Village of Lordstown, et al.
In the record
- Utility case, May 13, 2024. Utility case filed: Application of Ohio Power Company for approval of a Data Center Power tariff (Schedule DCT) and a Mobile Data Center tariff Public Utilities Commission of Ohio, 24-508-EL-ATA
Sources
- 1Data Center Costs, PUCO Case 24-0508-EL-ATA (case page and update)
Office of the Ohio Consumers' CounselTier 2 · OCC case page (adoption July 9, 2025; 85 percent minimum; term up to 12 years; November 2025 industry appeal to the Supreme Court of Ohio); Opinion and Order text as reproduced in the Supreme Court of Ohio appeal record, Case No. 2025-1458 · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Ohio Power Company for approval of a Data Center Power tariff (Schedule DCT) and a Mobile Data Center tariff." Last activity 2025-07-09. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-aep-ohio-dct-2025