Skip to content

Utility commission

Application of Ohio Power Company for approval of a Data Center Power tariff (Schedule DCT) and a Mobile Data Center tariff

Where it stands: Decided as of Jul 9, 2025

Draft research, not yet verified. Open a source to check any detail.

What it is

Schedule DCT covers new data center customers at 25 MW or more monthly maximum demand at a single location; a separate Mobile Data Center schedule covers mobile data centers (for example cryptocurrency miners) at 1 MW or more. Minimum billing demand is 85 percent of contract demand at full ramp (the adopted schedule applies a size-based formula that reaches 85 percent for the largest customers), over a term of up to 12 years including a four-year ramp-up. Customers must post collateral or other financial assurance and pay an exit fee on early termination. Existing data centers are grandfathered unless they expand past 25 MW. The Commission adopted the October 23, 2024 joint stipulation as modified; rehearing was denied September 3, 2025, and compliance tariffs took effect July 23, 2025.

The facts

Regulator
Public Utilities Commission of Ohio
Docket number
24-508-EL-ATA
Type
Large load tariff
Utility
AEP Ohio
State
Ohio
Filed
May 13, 2024
Status date
Jul 9, 2025
Large-load rules
Yes, for loads of 25 MW or more

Projects served by AEP Ohio

Related cases and proceedings

In the record

  1. Utility case, May 13, 2024. Utility case filed: Application of Ohio Power Company for approval of a Data Center Power tariff (Schedule DCT) and a Mobile Data Center tariff Public Utilities Commission of Ohio, 24-508-EL-ATA

Sources

  1. 1
    Data Center Costs, PUCO Case 24-0508-EL-ATA (case page and update)
    Office of the Ohio Consumers' Counsel
    Tier 2 · OCC case page (adoption July 9, 2025; 85 percent minimum; term up to 12 years; November 2025 industry appeal to the Supreme Court of Ohio); Opinion and Order text as reproduced in the Supreme Court of Ohio appeal record, Case No. 2025-1458 · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application of Ohio Power Company for approval of a Data Center Power tariff (Schedule DCT) and a Mobile Data Center tariff." Last activity 2025-07-09. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-aep-ohio-dct-2025