Project File
QTS New Albany 2 campus
New Albany,Licking County,OhioUnder constructionLast checked Nov 8, 2026
QTSDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Still to confirm: Capacity
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
QTS New Albany 2 campus is a under-construction data center project in New Albany, Licking County, Ohio. QTS is named as operator. No site capacity figure is published for this project.
QTS New Albany 2 campus is an under-construction data center project in New Albany, Licking County, Ohio. QTS is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in New Albany, Licking County, Ohio. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Ohio HB 646: Data center tax break caps, self-power, water and rate rules
The act covers data centers on a single parcel or contiguous, adjacent, or aggregated parcels requiring peak demand capacity greater than twenty-five megawatts at a single building or physical location; this project has no capacity figure on record, but the project's peak demand capacity at a single building or location and its parcel layout is not on record.
“"Data center" means one or more buildings or physical facilities or infrastructure, located on a single real property parcel or on contiguous, adjacent, or otherwise aggregated real property parcels requiring peak demand capacity that is greater than twenty-five megawatts at a single building or physical location and that are used primarily or exclusively for digital information services such as the management, storage, processing, and dissemination of electronic data and information through the use of computer systems, servers, networking equipment, and related components, including equipment cooling systems, or virtual currency mining.” (Sec. 4941.01(B))
Rule checks: Project is in Ohio. Still to check: size: unknown, who it covers: not checked
Bills and laws in Ohio
- HB 983 · In committee · Nov 10, 2026Data Center Accountability and Citizen Protection Act requirements
- HB 646 · Passed one chamber · Jun 10, 2026Data center tax break caps, self-power, water and rate rules
- HB 957 · In committee · Jun 3, 2026Ends new data center sales tax exemptions after September 2026
- SB 381 · In committee · Mar 25, 2026PUCO must approve data center grid interconnection agreements
- HB 784 · In committee · Mar 25, 2026Data centers report water use; bans water data in NDAs
- SB 374 · In committee · Mar 25, 2026Ends new data center sales tax exemptions after September 2026
Who's involved
- Developer and operatorQTS
Public records
2 records found so far. 7 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Decided · Jul 9, 2025Application of Ohio Power Company for approval of a Data Center Power tariff (Schedule DCT) and a Mobile Data Center tariff
Questions people ask
- Where is QTS New Albany 2 campus?
- QTS New Albany 2 campus is a data center project in New Albany, Licking County, Ohio.
- Who operates QTS New Albany 2 campus?
- QTS is named as the operator of QTS New Albany 2 campus.
- What stage is QTS New Albany 2 campus?
- QTS New Albany 2 campus is under construction.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Data center frequently asked questions
City of New Albany OhioTier 1 · Captured 2026-11-08 · Open the source - 2City of New Albany Ohio Data Center Zoning information sheet (May 2026)
City of New Albany Community Development DepartmentTier 1 · Captured 2026-11-08 · Open the source - 3Data Center Costs, PUCO Case 24-0508-EL-ATA (case page and update)
Office of the Ohio Consumers' CounselTier 2 · Captured 2026-11-08 · Open the source - 4
- 5EIA Form 861, Service Territory file, 2025 (final)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-11 · Open the source · Archived copy
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page