What it is

Proposed Schedule DCT, filed jointly by the three FirstEnergy Ohio utilities. Data center customers must take generation service from a competitive retail electric service (CRES) provider; a separate tariff for default service for data centers is to follow. The utility and the customer agree a monthly Contract Capacity; service may be suspended with Commission approval if the customer exceeds contract capacity by more than 1,000 kW, with added rules for customers using behind-the-meter generation. Minimum billing demand is the higher of 85 percent of contract capacity or actual usage, applied to all retail charges at the customer's service voltage, including distribution and transmission. The tariff also addresses collateral for new load, recovery of the cost of incremental transmission and distribution facilities, and exit fees.

The facts

Regulator
Public Utilities Commission of Ohio
Docket number
26-0697-EL-ATA
Type
Large load tariff
Utility
Toledo Edison
State
Ohio
Large-load rules
Yes

Related cases and proceedings

Sources

  1. 1
    Utility Files To Require Data Centers To Take Service From A Competitive Retail Supplier
    EnergyChoiceMatters
    Tier 3 · EnergyChoiceMatters, June 15, 2026 (filed Schedule DCT terms as quoted) and August 7, 2026 (Constellation opposition; PUCO Staff comments; Case 26-697-EL-ATA) · Open the source
  2. 2
    Constellation Opposes Utilities' Proposed Data Center Tariff That Would Require Data Centers To Be Served By Competitive Retail Suppliers
    EnergyChoiceMatters
    Tier 3 · EnergyChoiceMatters, June 15, 2026 (filed Schedule DCT terms as quoted) and August 7, 2026 (Constellation opposition; PUCO Staff comments; Case 26-697-EL-ATA) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Joint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)." Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-firstenergy-dct-2026-toledo-edison