Utility commission
Application of Duke Energy Ohio for approval of a data center rate class (Rate DC)
Where it stands: Pending before the commission as of Jul 27, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Proposed Rate DC covers data centers with monthly maximum demand of 25 MW or more, or requiring $10 million or more of Duke transmission or distribution investment. Contracts run 10 to 20 years. The minimum bill is negotiated case by case between 60 and 85 percent of reserved capacity; collateral is negotiated between 0 and 100 percent; the customer pays 100 percent of the non-network (dedicated) transmission facilities built to serve it. Customers must take generation from a competitive retail supplier, not Duke's standard service offer; a separate data center default service is to be created. Public comments were due October 22, 2026; PUCO Staff commented in October 2026 that the separate default service should apply to all data centers, not only new load.
The facts
- Regulator
- Public Utilities Commission of Ohio
- Docket number
- 26-0755-EL-ATA
- Type
- Large load tariff
- Utility
- Duke Energy Ohio
- State
- Ohio
- Filed
- Jul 27, 2026
- Status date
- Jul 27, 2026
- Large-load rules
- Yes, for loads of 25 MW or more
Projects served by Duke Energy Ohio
Related cases and proceedings
- Utility commission · Pending before the commissionApplication of The Dayton Power and Light Company (AES Ohio) for an increase in electric distribution rates, multi-year rate plan 2027-2029, with a stipulated Data Center Tariff
- Court case · PendingCity of Hilliard v. Ohio Environmental Protection Agency (fuel cell permit appeal)
- Utility commission · DecidedApplication of Ohio Power Company for approval of a Data Center Power tariff (Schedule DCT) and a Mobile Data Center tariff
- Utility commission · Pending before the commissionJoint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
- Utility commission · Pending before the commissionJoint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
- Utility commission · Pending before the commissionJoint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
- Court case · DecidedState ex rel. Bristolville 25 Developer, L.L.C., et al. v. Village of Lordstown, et al.
In the record
- Utility case, Jul 27, 2026. Utility case filed: Application of Duke Energy Ohio for approval of a data center rate class (Rate DC) Public Utilities Commission of Ohio, 26-0755-EL-ATA
Sources
- 1Data Center Tariff for Ohio Electric Customers (AEP Ohio and Duke Energy Ohio filings compared)
The Cincinnati ExchangeTier 3 · Cincinnati Exchange analysis of the filed application (Rate DC class; 25 MW or $10 million test; Exhibit C-2 terms); EnergyChoiceMatters, October 23, 2026 (PUCO Staff comments quoting the application) · Open the source - 2PUC Staff Seeks To Make Utility's Proposed Default Service For New Data Centers Applicable To All Data Centers
EnergyChoiceMattersTier 3 · Cincinnati Exchange analysis of the filed application (Rate DC class; 25 MW or $10 million test; Exhibit C-2 terms); EnergyChoiceMatters, October 23, 2026 (PUCO Staff comments quoting the application) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Duke Energy Ohio for approval of a data center rate class (Rate DC)." Last activity 2026-07-27. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-duke-ohio-rate-dc-2026