Utility commission
Application of The Dayton Power and Light Company (AES Ohio) for an increase in electric distribution rates, multi-year rate plan 2027-2029, with a stipulated Data Center Tariff
Where it stands: Pending before the commission as of Jul 21, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
The unopposed stipulation signed July 21, 2026 would create a data center tariff inside AES Ohio's 2027-2029 distribution rates. It covers data centers, including cryptocurrency mining, with aggregate monthly maximum demand above 25 MW. Minimum billing demand is at least 85 percent of agreed contract capacity, including through the ramp. The exit fee is the higher of minimum charges for at least 75 percent of the service term or the facilities' actual construction costs. Collateral combines ramp-period minimum charges, three years of service-term minimum charges, and the exit fee, backed by a parent or affiliate guarantee rated at least A- (S&P) and A3 (Moody's) with liquidity above ten times the requirement. Load under contracts signed before January 1, 2027 is excluded from the minimum-contract and collateral sections, and exit fee and collateral forfeiture revenue is directed to retail ratepayers.
The facts
- Regulator
- Public Utilities Commission of Ohio
- Docket number
- 25-0958-EL-AIR
- Type
- Rate case
- Utility
- AES Ohio
- State
- Ohio
- Status date
- Jul 21, 2026
- Large-load rules
- Yes, for loads of 25 MW or more
Related cases and proceedings
- Utility commission · Pending before the commissionApplication of Duke Energy Ohio for approval of a data center rate class (Rate DC)
- Court case · PendingCity of Hilliard v. Ohio Environmental Protection Agency (fuel cell permit appeal)
- Utility commission · DecidedApplication of Ohio Power Company for approval of a Data Center Power tariff (Schedule DCT) and a Mobile Data Center tariff
- Utility commission · Pending before the commissionJoint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
- Utility commission · Pending before the commissionJoint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
- Utility commission · Pending before the commissionJoint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
- Court case · DecidedState ex rel. Bristolville 25 Developer, L.L.C., et al. v. Village of Lordstown, et al.
Sources
- 1The OEC Joins AES Ohio Rate Case Settlement
Ohio Environmental CouncilTier 4 · Ohio Environmental Council, July 21, 2026 (signatory account: settlement introduces a new data center tariff); AltSS analysis of the stipulation (25 MW test; 85 percent minimum; exit fee and collateral formulas; guarantee ratings test) · Open the source - 2AES Ohio's proposed data-center tariff adds exit exposure to collateral
AltSSTier 3 · Ohio Environmental Council, July 21, 2026 (signatory account: settlement introduces a new data center tariff); AltSS analysis of the stipulation (25 MW test; 85 percent minimum; exit fee and collateral formulas; guarantee ratings test) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of The Dayton Power and Light Company (AES Ohio) for an increase in electric distribution rates, multi-year rate plan 2027-2029, with a stipulated Data Center Tariff." Last activity 2026-07-21. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-aes-ohio-rate-case-2026