Skip to content

Measured water use

Every water-use figure the public record holds for the data centers we track, project by project and year by year. Each figure is the operator's own reported number, from its environmental report, printed in the unit that report uses, with the report named on the row.

Operators publish a water-use figure for only 18 of the 1320 projects we track. This page lists every one of those figures: 75 in total, covering withdrawal, consumption, and discharge, each as the operator's own environmental report states it, in the unit the report uses. The other 1302 projects publish no water figure in any record we have found.

Consumption

Water that is not returned, mostly because it evaporates in cooling.

Discharge

Water the site sends back out, as the operator's report states it.

Filling and upkeep

One-time and yearly figures for a closed-loop cooling system, stated by the operator as anticipated design figures, not measured use.

  • Lancium Clean Campus data centers (Crusoe)
    Place
    Abilene, Texas
    Year
    Not stated
    Kind
    Annual maintenance
    Figure, as reported
    50,000 gallonsPer building per year: anticipated water use for cooling system maintenance and water quality purposes. An anticipated figure stated by the operator, not measured use
  • Lancium Clean Campus data centers (Crusoe)
    Place
    Abilene, Texas
    Year
    Not stated
    Kind
    Initial fill
    Figure, as reported
    1,000,000 gallonsPer building (each of the eight buildings): the initial fill of the closed-loop cooling system, sourced from the municipal water supply. An anticipated design figure stated by the operator, not measured use

How to read these figures

Withdrawal, consumption, and discharge are different quantities, so they sit in separate lists. Withdrawal is water taken in; consumption is water not returned, mostly because it evaporates; discharge is water sent back out. Adding one list to another would double count the same water.

Figures are printed in the unit the report uses, million gallons or megaliters, and are never converted or rounded. Compare figures within one unit, and within one kind: a withdrawal figure and a consumption figure for the same site describe different things.

Every figure here is reported by the operator itself, in its own environmental report. Operator reports are Tier 4 sources on this site: an interested party's own numbers, labeled as such, and each receipt says the research is draft, not yet verified. The one city-metered series in the record, from The Dalles, Oregon, is covered in the article below.

A project with no figure here is a project whose water use the public record does not state. Of the 1,320 projects we track, 18 publish a figure; the rest publish none that we have found.

The rest of the record for these projects

Water is one part of what a data center means for the place it lands in. Each project above has its own page, carrying the rest of its record from the same public sources: the jobs it committed to, the tax agreements it signed, and what officials and residents said about it. 17 of the 18 projects hold at least one tax agreement on record. Every one also carries an impact record covering property tax, tax breaks, electricity, water, jobs, community, neighbors, and voice.

This page sits under What it means for locals. The water calculator turns a daily figure into yearly terms, and residential electricity prices keeps the same kind of record for power bills. Our article on measured water use covers the one city-metered series, from The Dalles, Oregon. The projects themselves are ranked by size on largest projects by announced capacity, and the record's other rankings sit on lists from the record.

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

    Loudoun County's 128 data centers paid $684.8 million in equipment tax in fiscal 2024, at the full county rate. The record, from the county's books.

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

    Per SpaceX's Form 424B4, xAI Colossus 2 in Memphis runs two clusters online: about 110,000 GB200 processors at about 210 MW, and 110,000 GB300 processors at 220 MW, 430 MW in total.

Questions people ask

How much water do data centers use?
There is no single figure for the industry, because water use follows the cooling design: almost none for air-cooled and closed-loop designs, up to millions of gallons a day for a large evaporative system. What exists is a figure per site, stated by the operator or in a filing. The largest annual withdrawal on this page, among the figures stated in million gallons, is 1,746.4 million gallons at Google Council Bluffs data center campus in 2025, from the operator's own report.
What is the difference between withdrawal, consumption, and discharge?
Withdrawal is water a site takes in. Consumption is water that is not returned, mostly because it evaporates in cooling. Discharge is water the site sends back out. A site's withdrawal is roughly its consumption plus its discharge, and reports often give only one or two of the three, so this page keeps them in separate lists and never adds them together.
Are these figures metered?
No. Every figure on this page is reported by the operator itself, in its own environmental report, and each receipt says so. One series in the wider record is metered by a city: The Dalles, Oregon, where the city's own table shows the Google campus using 13,000 gallons in 2005 and 548.7 million gallons in 2025. That series comes from the city's records rather than an operator report, so it is not a row in this table; our article on measured water use covers it in full.
Why do so few projects publish a water figure?
A figure appears here only where an operator's own report or a public filing states one for the site. Most operators publish no site-by-site water figures, and the permits and agreements we hold for most projects state none, so the count stays low: 18 of the 1320 projects we track. A project with no figure on this page is a project whose water use the public record does not state, not a project that uses no water.

Sources

  1. 1
    Google 2025 Environmental Report (2024 data), Water use by data center location table
    Google
    Tier 4 · Open the source
  2. 2
    Google 2026 Environmental Report
    Google
    Tier 4 · Open the source
  3. 3
    An inside look at the Abilene AI data center
    Crusoe
    Tier 4 · Open the source

Back to What it means for locals

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Measured water use." Updated 2026-11-29. Accessed 2026-11-29. https://datacenterfactcheck.org/benefits/measured-water