Project File
Amazon New Carlisle Data Center Campus
New Carlisle,St. Joseph County,IndianaOperatingFirst public 2024Last checked Nov 8, 2026
AmazonDeveloper and operatorIndiana Michigan PowerElectric utilityAnthropicEnd user
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Amazon New Carlisle Data Center Campus is an operating data center project in New Carlisle, St. Joseph County, Indiana. Amazon is named as operator. It was first public in 2024. No site capacity figure is published for this project.
Amazon New Carlisle Data Center Campus is an operating data center project in New Carlisle, St. Joseph County, Indiana. Amazon is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in New Carlisle, St. Joseph County, Indiana. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Amazon New Carlisle Data Center CampusOperating
Bills and laws in Indiana
- HB 1333 · Passed one chamber · Feb 5, 2026Requires local agreement before data centers use a state tax exemption
- SB 257 · In committee · Jan 8, 2026Would bar the state commission from approving an electric rate increase to the extent it is related solely to the cost of serving a data center or a large facility with fewer than 50 full-time employees
- SB 79 · In committee · Jan 6, 2026Would require a state working group estimate of data center electricity demand, quarterly electricity-use reports from operators, and local permit disclosure of projected power and water use
- HB 1189 · In committee · Jan 5, 2026Would require a state incentive agreement with a qualified data center user to limit project bids and requests for proposals to labor unions or employers that have project labor agreements
- HB 1245 · In committee · Jan 5, 2026Requires a state study of data center demand effects on rates
- SB 83 · In committee · Dec 8, 2025Broad utility bill whose one data center provision repeals the sales and use tax exemption for certain data centers enacted in the 2025 session in HEA 1601
Who's involved
- Developer and operatorAmazon
- Electric utilityIndiana Michigan Power
- End userAnthropic
Public records
2 records found so far. 8 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Decided · Aug 27, 2026Application of Indiana Michigan Power Company for approval of modifications to its Large Power Tariff, Tariff LP
- Utility commission · Decided · Feb 19, 2025Verified Petition of Indiana Michigan Power Company for Approval of Modifications to Its Industrial Power Tariff, Tariff I.P.
Questions people ask
- Where is Amazon New Carlisle Data Center Campus?
- Amazon New Carlisle Data Center Campus is a data center project in New Carlisle, St. Joseph County, Indiana.
- Who operates Amazon New Carlisle Data Center Campus?
- Amazon is named as the operator of Amazon New Carlisle Data Center Campus.
- How big is Amazon New Carlisle Data Center Campus?
- The site covers 1,200 acres.
- What stage is Amazon New Carlisle Data Center Campus?
- Amazon New Carlisle Data Center Campus is operating. It was first public in 2024.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Regulatory and Policy Digest: Indiana commission approves settlement with new rules for large loads
Electric Power Research InstituteTier 2 · Captured 2026-11-07 · Open the source - 2Indiana Michigan Power Receives Order in Large Load Settlement
American Electric PowerTier 4 · Captured 2026-11-07 · Open the source - 3Order, Case No. U-21986 (Indiana Michigan Power Company, Large Power Tariff, Tariff LP)
Michigan Public Service CommissionTier 1 · Captured 2026-11-08 · Open the source - 4Michigan Commission Strengthens Large Load Rules for DTE Electric, Indiana Michigan Power
EnerKnolTier 3 · Captured 2026-11-08 · Open the source - 5Investor Meetings handout, September 2026 (large load tariff comparison table)
American Electric PowerTier 4 · Captured 2026-11-08 · Open the source - 6AWS plans $11 billion Indiana investment
About Amazon (Amazon)Tier 4 · Captured 2026-11-08 · Open the source - 7Amazon Web Services data centers in the US (community roundup)
About Amazon (Amazon)Tier 4 · Captured 2026-11-08 · Open the source - 8AWS opens giant data center for AI training
Network WorldTier 3 · Captured 2026-11-08 · Open the source - 9Form EIA-861 detailed data files 2023 (Service Territory and Utility Data)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-07 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page