Skip to content

Project File

Amazon New Carlisle Data Center Campus

New Carlisle,St. Joseph County,IndianaOperatingFirst public 2024Last checked Nov 8, 2026

AmazonDeveloper and operatorIndiana Michigan PowerElectric utilityAnthropicEnd user

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: Capacity
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Amazon New Carlisle Data Center Campus is an operating data center project in New Carlisle, St. Joseph County, Indiana. Amazon is named as operator. It was first public in 2024. No site capacity figure is published for this project.

Amazon New Carlisle Data Center Campus is an operating data center project in New Carlisle, St. Joseph County, Indiana. Amazon is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in New Carlisle, St. Joseph County, Indiana. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

2Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows St. Joseph County, Indiana.See every project on the map

The land, to scale

One football field
1,200 acres, about 908 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Amazon New Carlisle Data Center CampusOperating

Bills and laws in Indiana

All 8 in Bill Watch

Who's involved

Public records

2 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Amazon New Carlisle Data Center Campus?
Amazon New Carlisle Data Center Campus is a data center project in New Carlisle, St. Joseph County, Indiana.
Who operates Amazon New Carlisle Data Center Campus?
Amazon is named as the operator of Amazon New Carlisle Data Center Campus.
How big is Amazon New Carlisle Data Center Campus?
The site covers 1,200 acres.
What stage is Amazon New Carlisle Data Center Campus?
Amazon New Carlisle Data Center Campus is operating. It was first public in 2024.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Regulatory and Policy Digest: Indiana commission approves settlement with new rules for large loads
    Electric Power Research Institute
    Tier 2 · Captured 2026-11-07 · Open the source
  2. 2
    Indiana Michigan Power Receives Order in Large Load Settlement
    American Electric Power
    Tier 4 · Captured 2026-11-07 · Open the source
  3. 3
    Order, Case No. U-21986 (Indiana Michigan Power Company, Large Power Tariff, Tariff LP)
    Michigan Public Service Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Michigan Commission Strengthens Large Load Rules for DTE Electric, Indiana Michigan Power
    EnerKnol
    Tier 3 · Captured 2026-11-08 · Open the source
  5. 5
    Investor Meetings handout, September 2026 (large load tariff comparison table)
    American Electric Power
    Tier 4 · Captured 2026-11-08 · Open the source
  6. 6
    AWS plans $11 billion Indiana investment
    About Amazon (Amazon)
    Tier 4 · Captured 2026-11-08 · Open the source
  7. 7
    Amazon Web Services data centers in the US (community roundup)
    About Amazon (Amazon)
    Tier 4 · Captured 2026-11-08 · Open the source
  8. 8
    AWS opens giant data center for AI training
    Network World
    Tier 3 · Captured 2026-11-08 · Open the source
  9. 9
    Form EIA-861 detailed data files 2023 (Service Territory and Utility Data)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-07 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page