Utility commission
Application of Indiana Michigan Power Company for approval of modifications to its Large Power Tariff, Tariff LP
Where it stands: Decided as of Aug 27, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Tariff LP now carries specific terms for Large Load Customers with contract demand equal to or above 50 MW at one or more aggregated premises, or reasonably expected to grow to 50 MW. Approved terms include a 15-year contract requirement; limits on the load ramp period; a 90 percent minimum billing charge; stronger early termination charges (after year five, minimum bills for the remaining term, capped at five years); four years' notice for major capacity reductions; and increased collateral obligations. I&M must submit an ex parte filing before each new large load customer begins service, evaluate six cost allocation and rate design approaches, and create a dedicated rate class for data centers and similarly large customers in its next general rate case. Compliance tariff sheets were due within 30 days of the order.
The facts
- Regulator
- Michigan Public Service Commission
- Docket number
- U-21986
- Type
- Large load tariff
- Utility
- Indiana Michigan Power
- State
- Michigan
- Filed
- Oct 17, 2025
- Status date
- Aug 27, 2026
- Large-load rules
- Yes, for loads of 50 MW or more
Projects served by Indiana Michigan Power
Related cases and proceedings
- Utility commission · DecidedApplication of DTE Electric Company for approval of special contracts and related relief (Google LLC, Van Buren Township)
- Utility commission · DecidedApplication of DTE Electric Company for approval of special contracts with Green Chile Ventures LLC (primary supply agreement and energy storage agreement)
- Utility commission · DecidedApplication of Consumers Energy Company for approval of amendments to Rate GPD (Data Center Provision)
- Utility commission · DecidedVerified Petition of Indiana Michigan Power Company for Approval of Modifications to Its Industrial Power Tariff, Tariff I.P.
In the record
- Utility case, Oct 17, 2025. Utility case filed: Application of Indiana Michigan Power Company for approval of modifications to its Large Power Tariff, Tariff LP Michigan Public Service Commission, U-21986
Sources
- 1Order, Case No. U-21986 (Indiana Michigan Power Company, Large Power Tariff, Tariff LP)
Michigan Public Service CommissionTier 1 · Order of August 27, 2026 (caption; application of October 17, 2025; 50 MW large load definition; compliance sheets within 30 days); EnerKnol, August 28, 2026 (15-year term; ramp limits; termination charges; four years' notice; collateral; rate class directive); AEP investor handout, September 2026 (90 percent minimum billing charge; termination fee formula) · Open the source - 2Michigan Commission Strengthens Large Load Rules for DTE Electric, Indiana Michigan Power
EnerKnolTier 3 · Order of August 27, 2026 (caption; application of October 17, 2025; 50 MW large load definition; compliance sheets within 30 days); EnerKnol, August 28, 2026 (15-year term; ramp limits; termination charges; four years' notice; collateral; rate class directive); AEP investor handout, September 2026 (90 percent minimum billing charge; termination fee formula) · Open the source - 3Investor Meetings handout, September 2026 (large load tariff comparison table)
American Electric PowerTier 4 · Order of August 27, 2026 (caption; application of October 17, 2025; 50 MW large load definition; compliance sheets within 30 days); EnerKnol, August 28, 2026 (15-year term; ramp limits; termination charges; four years' notice; collateral; rate class directive); AEP investor handout, September 2026 (90 percent minimum billing charge; termination fee formula) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Indiana Michigan Power Company for approval of modifications to its Large Power Tariff, Tariff LP." Last activity 2026-08-27. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-imp-michigan-tariff-lp-2026