Application of Consumers Energy Company for approval of amendments to Rate GPD (Data Center Provision)

Where it stands: Decided as of Nov 6, 2025

Draft research, not yet verified. Open a source to check any detail.

What it is

Adds a Data Center Provision to Rate GPD for customers of 100 MW or more, or aggregated loads of 100 MW with individual sites of at least 20 MW under common ownership. Minimum contract term 15 years, with a ramp-up period of up to five years. Minimum billing demand 80 percent, payable regardless of use. Contracts extend automatically in five-year increments, with four years' notice required for termination, and an exit fee applies on early termination. Consumers must file an ex parte application before each large load customer takes service showing the new customer's costs are not subsidized by other customers, and each contract must carry the customer's transfer to any future large load rate. The Commission converted the case to a contested case on March 13, 2025 before approving the amendments.

The facts

Regulator
Michigan Public Service Commission
Docket number
U-21859
Type
Large load tariff
Utility
Consumers Energy
State
Michigan
Filed
Feb 7, 2025
Status date
Nov 6, 2025
Large-load rules
Yes, for loads of 100 MW or more

Projects served by Consumers Energy

Related cases and proceedings

In the record

  1. Utility case, Feb 7, 2025. Utility case filed: Application of Consumers Energy Company for approval of amendments to Rate GPD (Data Center Provision) Michigan Public Service Commission, U-21859

Sources

  1. 1
    MPSC approves terms of service between Consumers Energy and data centers, other very large customers (news release)
    Michigan Public Service Commission
    Tier 1 · MPSC news release of November 6, 2025 (100 MW threshold and 20 MW aggregation; 15-year term; 80 percent minimum billing demand; ramp; five-year extensions with four years' notice; per-customer ex parte filings) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application of Consumers Energy Company for approval of amendments to Rate GPD (Data Center Provision)." Last activity 2025-11-06. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-consumers-gpd-data-center-2025