New Carlisle, St. Joseph County, IndianaOperatingFirst public 2024Last checked Nov 8, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

2 of 2 records

2025

  • Utility proceedingDecidedOct 17, 2025Michigan Public Service Commission

    Application of Indiana Michigan Power Company for approval of modifications to its Large Power Tariff, Tariff LP

    Tariff LP now carries specific terms for Large Load Customers with contract demand equal to or above 50 MW at one or more aggregated premises, or reasonably expected to grow to 50 MW. Approved terms include a 15-year contract requirement; limits on the load ramp period; a 90 percent minimum billing charge; stronger early termination charges (after year five, minimum bills for the remaining term, capped at five years); four years' notice for major capacity reductions; and increased collateral obligations. I&M must submit an ex parte filing before each new large load customer begins service, evaluate six cost allocation and rate design approaches, and create a dedicated rate class for data centers and similarly large customers in its next general rate case. Compliance tariff sheets were due within 30 days of the order.

    U-21986

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Order of August 27, 2026 (caption; application of October 17, 2025; 50 MW large load definition; compliance sheets within 30 days); EnerKnol, August 28, 2026 (15-year term; ramp limits; termination charges; four years' notice; collateral; rate class directive); AEP investor handout, September 2026 (90 percent minimum billing charge; termination fee formula)

2024

  • Utility proceedingDecidedJul 19, 2024Indiana Utility Regulatory Commission

    Verified Petition of Indiana Michigan Power Company for Approval of Modifications to Its Industrial Power Tariff, Tariff I.P.

    Settled terms for very large customers: a large load is 70 MW or more at an individual site, or 150 MW or more aggregated across a company. Minimum contract term 12 years, with a five-year ramp-up period. Minimum monthly billing demand 80 percent. Increased collateral requirements. An exit fee equal to the minimum charge, capped at five years. Any agreed reduction of more than 20 percent of a customer's contracted peak capacity needs Commission approval before it takes effect.

    Cause No. 46097

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    EPRI Regulatory and Policy Digest, 2025-03-06, Indiana section (70/150 MW, 12-year term, 80 percent, collateral, exit fee cap, Cause No. 46097); AEP news release, 2025-02-19 (order approved with one modification)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Votes and minutes

    Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Regulatory and Policy Digest: Indiana commission approves settlement with new rules for large loads
    Electric Power Research Institute
    Tier 2 · Captured 2026-11-07 · Open the source
  2. 2
    Indiana Michigan Power Receives Order in Large Load Settlement
    American Electric Power
    Tier 4 · Captured 2026-11-07 · Open the source
  3. 3
    Order, Case No. U-21986 (Indiana Michigan Power Company, Large Power Tariff, Tariff LP)
    Michigan Public Service Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Michigan Commission Strengthens Large Load Rules for DTE Electric, Indiana Michigan Power
    EnerKnol
    Tier 3 · Captured 2026-11-08 · Open the source
  5. 5
    Investor Meetings handout, September 2026 (large load tariff comparison table)
    American Electric Power
    Tier 4 · Captured 2026-11-08 · Open the source
  6. 6
    AWS plans $11 billion Indiana investment
    About Amazon (Amazon)
    Tier 4 · Captured 2026-11-08 · Open the source
  7. 7
    Amazon Web Services data centers in the US (community roundup)
    About Amazon (Amazon)
    Tier 4 · Captured 2026-11-08 · Open the source
  8. 8
    AWS opens giant data center for AI training
    Network World
    Tier 3 · Captured 2026-11-08 · Open the source