Data Center Fact Check tracks 5 data center projects in South Fulton, Georgia as of November 2026: 3 proposed and 2 operating, totaling about 120 MW announced where a figure is published.
South Fulton has 5 tracked data centers. Their announced capacity totals about 120 MW where a figure is published. Of those, 3 proposed and 2 operating. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in South Fulton
- DataBank ATL5 (Atlanta)
OperatingSouth Fulton48 MW announced
- DataBank ATL6 (Atlanta)
OperatingSouth Fulton72 MW announced
- Stonewall Tell Data Center
ProposedSouth Fulton
- Vantage Data Center Stacks Road
ProposedSouth Fulton
- Vantage Data Center Westlake
ProposedSouth Fulton
Who serves this place
- Not collected yet.
More places in Fulton County
South Fulton is part of Fulton County.
Nearby places
- Union City4 data center projects tracked
- Fairburn2 data center projects tracked
- Alpharetta1 data center project tracked
- East Point1 data center project tracked
- Palmetto1 data center project tracked
Court cases and commission dockets in Georgia (8)
Bills and laws in Georgia
- SB 410 · Passed one chamber · Mar 6, 2026Ends new data center tax breaks, sets large load contract terms
- SB 34 · Died or failed · Feb 26, 2026Bars shifting data center power costs onto other utility customers
- HB 1387 · Died or failed · Feb 20, 2026Funds homestead exemption from property taxes collected on data centers
- SB 530 · Died or failed · Feb 19, 2026Deposits data center tax collections into a property tax relief fund
- HB 1323 · Died or failed · Feb 18, 2026Requires new data centers to operate as hybrid power facilities
- HB 1063 · Passed one chamber · Feb 17, 2026Requires utility contracts shielding other customers from data center costs
- SB 476 · Died or failed · Feb 12, 2026Ends new data center sales tax exemption certificates statewide
- HB 1059 · Died or failed · Jan 29, 2026Bans new data center permits through 2028, creates impact commission
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in South Fulton?
- Data Center Fact Check tracks 5 data center projects in South Fulton as of November 2026. Of those, 3 proposed and 2 operating.
- What is the biggest data center in South Fulton?
- By announced capacity, the biggest data center in South Fulton is DataBank ATL6 (Atlanta), announced at 72 MW. It is operating.
- How much power do data centers in South Fulton use?
- The 5 projects tracked in South Fulton have announced about 120 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "South Fulton." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ga-south-fulton
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page