County Card
Data centers in Effingham County, Georgia
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 1 data center project in Effingham County, Georgia as of November 2026, totaling about 3,200 MW announced where a figure is published.
Effingham County has 1 tracked data center project. Their announced capacity totals about 3,200 MW where a figure is published. The project here is OpenAI Project Camellia, in permitting. Every figure comes from the public record linked on this page.
OpenAI Project Camellia video · 1 min 56 sec
Data center projects in Effingham County
- OpenAI Project Camellia
In permittingRincon3,200 MW announced
Who serves this place
- Not collected yet.
Places in and around Effingham County
Effingham County is part of Georgia.
Cities and towns
- Rincon1 data center project tracked
Nearby places
- Fulton County26 data center projects tracked
- Douglas County14 data center projects tracked
- Bartow County4 data center projects tracked
- Fayette County4 data center projects tracked
- Coweta County3 data center projects tracked
- Gwinnett County3 data center projects tracked
- Richmond County3 data center projects tracked
- Carroll County2 data center projects tracked
- Clayton County2 data center projects tracked
- Columbia County2 data center projects tracked
- Early County2 data center projects tracked
- Floyd County2 data center projects tracked
For homeowners
What the projects here mean if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
Property tax
The county’s DRI filing estimates $20 million a year in local tax revenue from the project, and OpenAI expects to be the county’s largest taxpayer.
Comes to the community
Money for schools and services
OpenAI has committed $80 million in community benefits over the life of the project, separate from its tax payments.
Comes from the community
Electricity bill
OpenAI states it will pay the full cost of the infrastructure and electric service this project needs, and Georgia PSC rules bar passing those costs to existing ratepayers.
Comes from the community
Water
The project will cool with a closed-loop system, and the county filing puts its water demand at 30,000 gallons a day.
Comes from the community
Jobs
The county’s DRI filing estimates 400 full-time employees at build-out, and OpenAI says the project will create thousands of construction and permanent on-site jobs.
Comes from the community
Court cases and commission dockets in Georgia (8)
Bills and laws in Georgia
- SB 410 · Passed one chamber · Mar 6, 2026Ends new data center tax breaks, sets large load contract terms
- SB 34 · Died or failed · Feb 26, 2026Bars shifting data center power costs onto other utility customers
- HB 1387 · Died or failed · Feb 20, 2026Funds homestead exemption from property taxes collected on data centers
- SB 530 · Died or failed · Feb 19, 2026Deposits data center tax collections into a property tax relief fund
- HB 1323 · Died or failed · Feb 18, 2026Requires new data centers to operate as hybrid power facilities
- HB 1063 · Passed one chamber · Feb 17, 2026Requires utility contracts shielding other customers from data center costs
- SB 476 · Died or failed · Feb 12, 2026Ends new data center sales tax exemption certificates statewide
- HB 1059 · Died or failed · Jan 29, 2026Bans new data center permits through 2028, creates impact commission
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Effingham County?
- Data Center Fact Check tracks 1 data center project in Effingham County as of November 2026.
- What is the biggest data center in Effingham County?
- By announced capacity, the biggest data center in Effingham County is OpenAI Project Camellia, announced at 3,200 MW. It is in permitting.
- How much power do data centers in Effingham County use?
- The 1 projects tracked in Effingham County have announced about 3,200 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1DRI #4801 Information Form Part 2: Project Camellia
Georgia Department of Community AffairsTier 1 · Open the source - 2
- 3
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Effingham County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ga-effingham
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page