Data centers in Jefferson County, Alabama
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 4 data center projects in Jefferson County, Alabama as of November 2026: 1 proposed, 1 approved and 1 under construction, totaling about 1,505 MW announced where a figure is published.
Jefferson County has 4 tracked data centers. Their announced capacity totals about 1,505 MW where a figure is published. Of those, 1 proposed, 1 approved and 1 under construction. Every figure comes from the public record linked on this page.
Data center projects in Jefferson County
- DC BLOX Birmingham Data Center
OperatingBirmingham5 MW announced
- Nebius Birmingham AI Factory
Under constructionBirmingham300 MW announced
- Project Marvel
ApprovedBessemer1,200 MW announced
- QTS Bessemer (Bessemer; listed as in development)
ProposedBessemer
Who serves this place
- Not collected yet.
A data center is proposed in Jefferson County
1 project here is at the announced or proposed stage. Before the hearing, the resident checklist walks through what to check: the proposal's documents, the local rules where you live, the tax agreement, and the recorded votes.
Places in and around Jefferson County
Jefferson County is part of Alabama.
Cities and towns
- Bessemer2 data center projects tracked
- Birmingham2 data center projects tracked
Nearby places
- Madison County2 data center projects tracked
- Mobile County2 data center projects tracked
- Tuscaloosa County2 data center projects tracked
- Jackson County1 data center project tracked
- Lee County1 data center project tracked
- Lowndes County1 data center project tracked
- Montgomery County1 data center project tracked
- Shelby County1 data center project tracked
Court cases and commission dockets in Alabama (4)
Bills and laws in Alabama
- SB 270 · Signed into law · Apr 17, 2026Requires data center power contracts to repay their own costs
- SB 265 · Died or failed · Apr 9, 2026Senate companion to HB 399 on data center tax abatements (not enacted)
- HB 399 · Signed into law · Apr 9, 2026Limits data center tax abatements to 20 years, with a community-investment path to 30, and extends the program sunset to 2032
- HB 403 · Died or failed · Mar 31, 2026House companion to SB 270 on PSC review of data center power contracts (not enacted)
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Jefferson County?
- Data Center Fact Check tracks 4 data center projects in Jefferson County as of November 2026. Of those, 1 proposed, 1 approved and 1 under construction.
- What is the biggest data center in Jefferson County?
- By announced capacity, the biggest data center in Jefferson County is Project Marvel, announced at 1,200 MW. It is approved.
- How much power do data centers in Jefferson County use?
- The 4 projects tracked in Jefferson County have announced about 1,505 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Jefferson County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-al-jefferson
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page