AlabamaSenate2026 Regular SessionBill
SB 270: Requires data center power contracts to repay their own costs
Official title: Electric Utilities; review by Public Service Commission of certain contracts with large load data centers further provided for
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Signed into law as of Apr 17, 2026. The official record says: signed into law.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (done)
- Signed into law (current stage)
- In effect (not reached)
What it does
Service terms
“The determination of whether a contract between a large load data center customer and a utility promotes positive benefits under subdivision (b)(2) includes considerations such as: (1) Whether the pricing and terms and conditions of the contract could lower costs for other customers of the utility; (2) Whether the large load data center customer is expected to increase the efficiency of the utility's power system; and (3) Whether the large load data center customer promotes or contributes to economic growth in the community where the premises of the large load data center customer is located.”
Enrolled act, Section 1, new Code Section 37-4-22.1(c)
Who pays for grid costs
“a contract for retail electric service between a utility and a person that qualifies as a large load data center customer is consistent with the public interest where the commission determines that the contract pricing and contract terms and conditions over the contract term are expected to: (1) Provide for the recovery of the incremental costs of retail electric service to the large load data center customer's premises from the large load data center customer…”
Enrolled act, Section 1, new Code Section 37-4-22.1(b) and (b)(1)
Definition · threshold 150 MW
Applies to: large load data center customers
“(2) LARGE LOAD DATA CENTER CUSTOMER. A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.”
Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2)
Effective date
“Section 2. This act shall become effective on October 1, 2026.”
Enrolled act, Section 2
Definition
“(1) INCREMENTAL COSTS OF RETAIL ELECTRIC SERVICE. The additional costs associated with the generation, transmission, distribution, sale, or furnishing of electricity to a large load data center customer, including fuel costs and taxes, which the utility would not incur but for the large load data center customer contract.”
Enrolled act, Section 1, new Code Section 37-4-22.1(a)(1)
Service terms
“(2) Promote positive benefits to other retail electric customers of the utility.”
Enrolled act, Section 1, new Code Section 37-4-22.1(b)(2)
Who it touches (10)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Applied Digital Delta Forge 2
The act covers large load data center customers, customers of the utility that have executed a contract for retail electric service requiring the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, that meet the data processing center definition and operate solely for data processing; this project has 210 MW on record (IT load), but the project's expected total peak demand and whether it has executed a retail electric service contract of that size is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2))
Rule checks: Project is in Alabama; 210 MW on record (it load), threshold 150 MW (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Beacon Calvert Infrastructure Hub
The act covers large load data center customers, customers of the utility that have executed a contract for retail electric service requiring the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, that meet the data processing center definition and operate solely for data processing; this project has no capacity figure on record, but the project's expected total peak demand and whether it has executed a retail electric service contract of that size is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2))
Rule checks: Project is in Alabama. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Google Jackson County Data Center
The act covers large load data center customers, customers of the utility that have executed a contract for retail electric service requiring the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, that meet the data processing center definition and operate solely for data processing; this project has no capacity figure on record, but the project's expected total peak demand and whether it has executed a retail electric service contract of that size is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2))
Rule checks: Project is in Alabama. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Meta Huntsville Data Center
The commission review covers a utility customer that has executed a retail electric service contract requiring the utility to serve an expected total peak demand of 150 megawatts or greater, and neither a peak demand figure nor a retail electric service contract for this campus is on record.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Ala. Code Sec. 37-4-22.1(a)(2))
Rule checks: Project is in Alabama. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Meta Montgomery Data Center
The act covers large load data center customers, customers of the utility that have executed a contract for retail electric service requiring the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, that meet the data processing center definition and operate solely for data processing; this project has no capacity figure on record, but the project's expected total peak demand and whether it has executed a retail electric service contract of that size is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2))
Rule checks: Project is in Alabama. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Nebius Birmingham AI Factory
The act covers large load data center customers, customers of the utility that have executed a contract for retail electric service requiring the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, that meet the data processing center definition and operate solely for data processing; this project has 300 MW announced on record, but the project's expected total peak demand and whether it has executed a retail electric service contract of that size is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2))
Rule checks: Project is in Alabama; 300 MW on record (announced), threshold 150 MW (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Project Marvel
The act covers large load data center customers, customers of the utility that have executed a contract for retail electric service requiring the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, that meet the data processing center definition and operate solely for data processing; this project has 1,200 MW announced on record, but the project's expected total peak demand and whether it has executed a retail electric service contract of that size is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2))
Rule checks: Project is in Alabama; 1,200 MW on record (announced), threshold 150 MW (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Bessemer (Bessemer; listed as in development)
The act covers large load data center customers, customers of the utility that have executed a contract for retail electric service requiring the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, that meet the data processing center definition and operate solely for data processing; this project has no capacity figure on record, but the project's expected total peak demand and whether it has executed a retail electric service contract of that size is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2))
Rule checks: Project is in Alabama. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Red Clay Technology Center Campus
The act covers large load data center customers, customers of the utility that have executed a contract for retail electric service requiring the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, that meet the data processing center definition and operate solely for data processing; this project has no capacity figure on record, but the project's expected total peak demand and whether it has executed a retail electric service contract of that size is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2))
Rule checks: Project is in Alabama. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026University of Alabama High Performance Computing and Data Center
The act covers large load data center customers, customers of the utility that have executed a contract for retail electric service requiring the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, that meet the data processing center definition and operate solely for data processing; this project has no capacity figure on record, but the project's expected total peak demand and whether it has executed a retail electric service contract of that size is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A customer of the utility which has executed a contract for retail electric service with the utility which requires the utility to serve an expected total peak demand of 150 megawatts or greater at one or more contiguous parcels of land, meets the definition of a data processing center under Section 40-9B-3, and operates solely for the purpose of data processing.” (Enrolled act, Section 1, new Code Section 37-4-22.1(a)(2))
Rule checks: Project is in Alabama. Still to check: size: unknown, who it covers: not checked
Other projects we track in Alabama (5), not affected
- AUBix Data CenterOperating
- DC BLOX Birmingham Data CenterOperating
- DC BLOX Huntsville Data CenterOperating
- Digi Power X Columbiana AI Data CenterUnder construction
- Edged Project GatewayProposed
Who acted
- Primary sponsorLance BellSenate
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- · SenateFirst Read: 05-Feb-26; RFD: Fiscal Responsibility and Economic DevelopmentStage: In committee
- · SenatePassed the Senate (certification in enrolled act: Senate 12-Mar-26)Stage: Passed one chamber
- · HouseAmended and passed by the House of Representatives: 08-Apr-26
- · SenateSenate concurred in House amendment 08-Apr-26Stage: Passed both chambers
- Approved by the Governor; assigned Act No. 2026-610Stage: Signed into law
- Act effective October 1, 2026 (Section 2 of the act)Stage: In effect
More from Alabama
- HB 399 · Signed into lawLimits data center tax abatements to 20 years, with a community-investment path to 30, and extends the program sunset to 2032
- SB 265 · Died or failedSenate companion to HB 399 on data center tax abatements (not enacted)
- HB 403 · Died or failedHouse companion to SB 270 on PSC review of data center power contracts (not enacted)
Sources
- 1Alabama Legislature acts listing: SB 270, Act No. 2026-610
Alabama Legislature (ALISON, alison.legislature.state.al.us)Tier 1 · Open the source - 2
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "SB 270: Requires data center power contracts to repay their own costs." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/al-2026-sb-270
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page