Project File
Digi Power X Columbiana AI Data Center
Columbiana,Shelby County,AlabamaUnder constructionLast checked Nov 8, 2026
Digi Power XDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Still to confirm: Electric utility
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Digi Power X Columbiana AI Data Center is a under-construction data center project in Columbiana, Shelby County, Alabama. Digi Power X is named as operator. It was announced at 40 MW.
Digi Power X Columbiana AI Data Center is an under-construction data center project in Columbiana, Shelby County, Alabama. Digi Power X is named as operator. It was announced at 40 MW. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Columbiana, Shelby County, Alabama. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Bills and laws in Alabama
- SB 270 · Signed into law · Apr 17, 2026Requires data center power contracts to repay their own costs
- SB 265 · Died or failed · Apr 9, 2026Senate companion to HB 399 on data center tax abatements (not enacted)
- HB 399 · Signed into law · Apr 9, 2026Limits data center tax abatements to 20 years, with a community-investment path to 30, and extends the program sunset to 2032
- HB 403 · Died or failed · Mar 31, 2026House companion to SB 270 on PSC review of data center power contracts (not enacted)
Who's involved
- Developer and operatorDigi Power X
Power
Capacity, as announced or filed
- 40 MW · Full facility (Phases 1 and 2)Oct 2026 · what the figure measures is not stated
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Digi Power X Columbiana AI Data Center?
- Digi Power X Columbiana AI Data Center is a data center project in Columbiana, Shelby County, Alabama.
- Who operates Digi Power X Columbiana AI Data Center?
- Digi Power X is named as the operator of Digi Power X Columbiana AI Data Center.
- How big is Digi Power X Columbiana AI Data Center?
- Digi Power X Columbiana AI Data Center was announced at 40 MW of capacity.
- What stage is Digi Power X Columbiana AI Data Center?
- Digi Power X Columbiana AI Data Center is under construction.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Digi Power X Announces $200 Million Debt Financing Commitment to Support Completion of Alabama AI Data Center and Provides Expansion Update
Digi Power X Inc. (via ACCESS Newswire)Tier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page