Data center court cases and dockets
A docket is a case's public file. These are the lawsuits and the utility commission proceedings (rate cases, large-load rules, agreements) that touch data centers, newest activity first. Each links to its source.
211 dockets, page 6 of 6
Cases and proceedings
Utility commissionPending before the commissionLarge loads
Investigation of possible ratepayer protections and cost recovery mechanisms for servicing large demand project applicants or customers of Commonwealth Edison Company
Illinois Commerce Commission · Docket 26-0364 · ComEd · Illinois
Utility commissionPending before the commissionLarge loads
Joint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
Public Utilities Commission of Ohio · Docket 26-0697-EL-ATA · The Cleveland Electric Illuminating Company · Ohio
Utility commissionPending before the commissionLarge loads
Joint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
Public Utilities Commission of Ohio · Docket 26-0697-EL-ATA · Ohio Edison · Ohio
Utility commissionPending before the commissionLarge loads
Joint application of Ohio Edison Company, The Cleveland Electric Illuminating Company and The Toledo Edison Company for approval of a Data Center Tariff (Schedule DCT)
Public Utilities Commission of Ohio · Docket 26-0697-EL-ATA · Toledo Edison · Ohio
Utility commissionIn effectLarge loads
Large Power Contract Service (LPCS) Tariff, Wyoming Electric (Cheyenne Light, Fuel and Power)
Wyoming Public Service Commission · Cheyenne Light Fuel & Power · Wyoming
Utility commissionPending before the commissionLarge loads
Minnesota Power petition for a very large customer tariff under Minn. Stat. 216B.1622
Minnesota Public Utilities Commission · Docket 26-126 · Minnesota Power · Minnesota
Court caseDecided
Organizacion Comunidad de Alviso v. City of San Jose (Microsoft Corporation et al., real parties in interest)
California Court of Appeal, Sixth Appellate District · Docket H046458 · Santa Clara County · California
About: Microsoft San Jose data center (Alviso)
Utility commissionPending before the commissionLarge loads
Otter Tail Power Company petition for a very large customer class and a data center rate schedule
Minnesota Public Utilities Commission · Docket 26-211 · Otter Tail Power Company · Minnesota
Utility commissionPending before the commissionLarge loads
RTP Revenue Credit and Allocation Methodology
Georgia Public Service Commission · Docket 57171 · Georgia Power Company · Georgia
Court caseDecided
State ex rel. Bristolville 25 Developer, L.L.C., et al. v. Village of Lordstown, et al.
Supreme Court of Ohio · Docket No. 2025-1497 (Slip Opinion No. 2026-Ohio-4073) · Trumbull County · Ohio
Court caseDecided
Town of Leesburg and Loudoun County voluntary settlement agreement validation (Compass Creek annexation)
Special Court for Loudoun County, Virginia (three-judge panel appointed by the Supreme Court of Virginia; hearing in Loudoun County Circuit Court) · Loudoun County · Virginia
About: Microsoft Leesburg data center campus (Compass Creek)
Sources on this page
- 1Verified Petition to Intervene of the Citizens Utility Board, ICC Docket No. 26-0364
Illinois Commerce Commission (docket document)Tier 1 · Draft research, not yet verified · Open the source - 2ICC looks to develop consumer protection framework amid increase in large energy demand (press release)
Illinois Commerce CommissionTier 1 · Draft research, not yet verified · Open the source - 3ComEd customers could be on hook for billions in data center-related costs, according to consumer advocates' review of utility's records
Citizens Utility BoardTier 4 · Draft research, not yet verified · Open the source - 4Utility Files To Require Data Centers To Take Service From A Competitive Retail Supplier
EnergyChoiceMattersTier 3 · Draft research, not yet verified · Open the source - 5Constellation Opposes Utilities' Proposed Data Center Tariff That Would Require Data Centers To Be Served By Competitive Retail Suppliers
EnergyChoiceMattersTier 3 · Draft research, not yet verified · Open the source - 6Black Hills Corp. Executes Definitive Agreements to Serve Google's Planned Data Center in Cheyenne, Wyoming (press release, Exhibit 99.1 to Form 8-K)
Black Hills Corp.Tier 1 · Draft research, not yet verified · Open the source - 7Very large electric customers and the PUC process
Minnesota Public Utilities CommissionTier 1 · Draft research, not yet verified · Open the source - 8Data Centers to Pay Fair Share: PUC enacts protections for Xcel customers
Citizens Utility Board of MinnesotaTier 4 · Draft research, not yet verified · Open the source - 9Organizacion Comunidad de Alviso v. City of San Jose, 60 Cal.App.5th 783 (2021), Appeal No. H046458
California Court of Appeal, Sixth Appellate DistrictTier 1 · Draft research, not yet verified · Open the source - 10Commission Calendar, November 2026 (Docket No. 57171 hearing, November 12, 2026)
Georgia Public Service CommissionTier 1 · Draft research, not yet verified · Open the source - 11State ex rel. Bristolville 25 Developer, L.L.C. v. Village of Lordstown, Slip Opinion No. 2026-Ohio-4073 (No. 2025-1497)
Supreme Court of OhioTier 1 · Draft research, not yet verified · Open the source - 12News Release: Voluntary Settlement Agreement Between Town of Leesburg and Loudoun County Validated
Town of Leesburg, VirginiaTier 1 · Draft research, not yet verified · Open the source - 13Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
Virginia Commission on Local Government (Department of Housing and Community Development)Tier 1 · Draft research, not yet verified · Open the source