QTS Salem Township (Salem Township; listed as in consideration)
Luzerne County,PennsylvaniaProposedFirst public 2026Last checked Nov 14, 2026
QTSOperator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: City or address
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
QTS Salem Township (Salem Township; listed as in consideration) is a proposed data center project in Luzerne County, Pennsylvania. QTS is named as operator. It was first public in 2026. No site capacity figure is published for this project.
QTS Salem Township (Salem Township; listed as in consideration) is a proposed data center project in Luzerne County, Pennsylvania. QTS is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Luzerne County, Pennsylvania. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of QTS Salem Township (Salem Township; listed as in consideration)Proposed
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Pennsylvania HB 1834: Regulates commercial data centers and their energy use
The act covers commercial data centers in Pennsylvania, facilities used for processing, storing, retrieving, or transmitting data with a peak demand of 25 megawatts or greater that are interconnected to a public utility; this project has no capacity figure on record, but the project's peak demand and its interconnection to a public utility is not on record. Status part: the bill's status (passed House; in Senate committee) means its text is not yet operative law, and the text part below is read from the bill as passed one chamber. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“A facility, campus of facilities or array of interconnected facilities in this Commonwealth that meets all of the following: (1) Is used by a business entity or other enterprise to operate, manage or maintain a computer, group of computers or other organized assembly of hardware and software for the primary purpose of processing, storing, retrieving or transmitting data. (2) Has a peak demand of 25 megawatts or greater. (3) Is interconnected to a public utility at a single point of interconnection or multiple points of interconnection or is interconnected to multiple public utilities within this Commonwealth through multiple points of interconnection.” (Section 2, definition of commercial data center)
Rule checks: Project is in Pennsylvania. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Pennsylvania HB 2650: Requires state certification for data center tax benefits
The act covers computer data centers in Pennsylvania, facilities predominantly used to house working servers or similar data storage systems, when an owner or operator seeks GRID certification and its tax benefits; this project has no capacity figure on record, but whether its owner or operator has applied for or holds GRID certification is not on record. Status part: the bill's status (passed House; in Senate committee) means its text is not yet operative law, and the text part below is read from the bill as passed one chamber. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“All or part of a facility that may be composed of one or more businesses, owners or tenants, that is or will be predominantly used to house working servers or similar data storage systems and that may have uninterruptible energy supply or generator backup power, or both closed-loop cooling systems, towers and other temperature control infrastructure.” (Section 2902-D.1, definition of computer data center)
Rule checks: Project is in Pennsylvania. Still to check: who it covers: not checked
Bills and laws in Pennsylvania
- HB 2888 · In committee · Nov 4, 2026Requires reporting and benefit plans for hyperscale data centers
- HB 2674 · Passed one chamber · Oct 26, 2026Defines commercial data centers in the utility code
- SB 1408 · In committee · Oct 5, 2026Bans secrecy agreements between agencies and data centers
- SB 1345 · In committee · Sep 30, 2026Lets towns pause new large data center applications
- HB 2359 · Passed one chamber · Jul 10, 2026Bans secrecy agreements between agencies and data centers
- HB 2198 · Passed one chamber · Jun 26, 2026Repeals the data center equipment tax incentive program
Who's involved
- OperatorQTS
Public records
2 records found so far. 8 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Pending before the commission · Nov 10, 2026Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation (formal complaint on large load and data center costs)
- Utility commission · Pending before the commission · Nov 10, 2026Petition of PPL Electric Utilities Corporation for Approval of Its Non-Bypassable Customer Protection Transmission Rider, Elimination of Its Transmission Service Charge, Changes to Its Generation Supply Charges, Changes to Its Retail Tariff, and Changes to Its Electric Generation Supplier Coordination Tariff
Questions people ask
- Where is QTS Salem Township (Salem Township; listed as in consideration)?
- QTS Salem Township (Salem Township; listed as in consideration) is a data center project in Luzerne County, Pennsylvania.
- Who operates QTS Salem Township (Salem Township; listed as in consideration)?
- QTS is named as the operator of QTS Salem Township (Salem Township; listed as in consideration).
- How big is QTS Salem Township (Salem Township; listed as in consideration)?
- The site covers 1,700 acres.
- What stage is QTS Salem Township (Salem Township; listed as in consideration)?
- QTS Salem Township (Salem Township; listed as in consideration) is proposed. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1PUC docket page, P-2026-3065185 (PPL Customer Protection Transmission Rider petition)
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source - 2RESA Prehearing Memorandum, P-2026-3065185
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 3PUC docket page, C-2026-3065756 (Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation)
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 4PPLICA Petition to Intervene, C-2026-3065756
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 5QTS data center locations (operator’s own list)
QTSTier 2 · Captured 2026-11-10 · Open the source · Archived copy - 6
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page