What it is

The Office of Consumer Advocate alleges existing customers are paying new and higher costs caused by data center additions on PPL’s system and in PJM, and are receiving service frequently interrupted or curtailed because of data center interconnection. It says Rate Schedule LP-6 does not protect enough and asks the Commission to make its model tariff guidelines mandatory for PPL: mandatory interruptible rates for data centers; pre-emergency and emergency load shed plans; classification of computational loads as critical or non-critical; affordability protections including ongoing contributions to the Universal Service Program; classification by end use (computational load) instead of only by connection above 69 kV; binding generator commitments or matching capacity from computational customers; a battery storage network for peaks; a definition of but-for costs for transmission and distribution upgrades; and a test of whether capacity and transmission rate design, including Reliability Backstop Procurement and Interim Resource Adequacy Service costs, protects other customers. The model tariff threshold is 50 MW for a single load or 100 MW in aggregate. Governor Shapiro intervened on October 16, 2026; Amazon Data Services and the Data Center Coalition intervened on November 3, 2026.

The facts

Regulator
Pennsylvania Public Utility Commission
Docket number
C-2026-3065756
Type
Other
Utility
PPL Electric Utilities Corp
State
Pennsylvania
Filed
Oct 2, 2026
Status date
Nov 10, 2026
Large-load rules
Yes, for loads of 50 MW or more

Projects served by PPL Electric Utilities Corp

Related cases and proceedings

In the record

  1. Utility case, Oct 2, 2026. Utility case filed: Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation (formal complaint on large load and data center costs) Pennsylvania Public Utility Commission, C-2026-3065756

Sources

  1. 1
    PUC docket page, C-2026-3065756 (Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation)
    Pennsylvania Public Utility Commission
    Tier 1 · PUC docket page, Case Summary (docket, Active, Date Filed 10/2/2026) and Daily Actions, 11/10/2026 (consolidated Scheduling Order); PPLICA Petition to Intervene, filed 2026-10-22, complaint summary at pages 1-2 and relief at pages 3-4 and 77-79 · Open the source
  2. 2
    PPLICA Petition to Intervene, C-2026-3065756
    Pennsylvania Public Utility Commission
    Tier 1 · PUC docket page, Case Summary (docket, Active, Date Filed 10/2/2026) and Daily Actions, 11/10/2026 (consolidated Scheduling Order); PPLICA Petition to Intervene, filed 2026-10-22, complaint summary at pages 1-2 and relief at pages 3-4 and 77-79 · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation (formal complaint on large load and data center costs)." Last activity 2026-11-10. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-ppl-oca-complaint-2026