Stak Energy North Slope Data Center (proposed)

North Slope Borough,AlaskaProposedFirst public 2026Filing entity: Stak EnergyLast checked Nov 10, 2026

Stak EnergyDeveloper and operator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

3 of 6 details confirmed

  • Confirmed: County
  • Confirmed: Stage
  • Confirmed: First public date
  • Still to confirm: City or address
  • Still to confirm: Capacity
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Stak Energy North Slope Data Center (proposed) is a proposed data center project in North Slope Borough, Alaska. Stak Energy is named as operator. It was first public in 2026. No site capacity figure is published for this project.

Stak Energy North Slope Data Center (proposed) is a proposed data center project in North Slope Borough, Alaska. Stak Energy is named as operator. No site capacity figure is published for this project. 3 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in North Slope Borough, Alaska. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

1Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Site-level positionPin placed from the position we have on file, inside North Slope Borough, Alaska.See every project on the map

The land, to scale

One football field
640 acres, about 484 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · DecisionAlaska Department of Natural Resources, Division of Oil and Gas: Preliminary Decision proposing a 50-year negotiated lease of state land to STAK Energy Corporation under AS 38.05.070(d) for the STAK Energy Campus. The comment period was later extended to July 17, 2026; no final decision had issue...ADL 422741
  2. · FilingFiled with Alaska Department of Natural Resources, Division of Oil and Gas for Stak Energy North Slope Data Center (proposed)ADL 422741
  3. · New projectFirst public record of Stak Energy North Slope Data Center (proposed)Proposed

Bills and laws in Alaska

Open Bill Watch

Who's involved

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Alaska Department of Natural Resources, Division of Oil and Gas, ADL 422741

    Stated in the filing
    $500 million
    Stated in the filing
    715.4 acres
    Stated in the filing
    640 acres
    Stated in the filingEstimated
    1000-3000 MWThe decision states the campus's natural-gas-fired generation is designed to produce 1-3 GW, fully behind the meter. This is a design range for on-site generation, not a stated fleet total, so it is rowed as a document fact only and no project_capacity row is written.
    Stated in the filing
    60 jobs

Public records

1 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Stak Energy North Slope Data Center (proposed)?
Stak Energy North Slope Data Center (proposed) is a data center project in North Slope Borough, Alaska.
Who operates Stak Energy North Slope Data Center (proposed)?
Stak Energy is named as the operator of Stak Energy North Slope Data Center (proposed).
How big is Stak Energy North Slope Data Center (proposed)?
The site covers 640 acres.
What stage is Stak Energy North Slope Data Center (proposed)?
Stak Energy North Slope Data Center (proposed) is proposed. It was first public in 2026.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Preliminary Decision ADL 422741: STAK Energy Corporation, proposed land lease for the STAK Energy Campus, North Slope
    Alaska Department of Natural Resources, Division of Oil and Gas
    Tier 1 · Captured 2026-11-10 · Open the source
  2. 2
    After Local Zoning: Next Steps for Alaska in Data Center Development
    Davis Wright Tremaine LLP
    Tier 2 · Captured 2026-11-08 · Open the source