Project File

Karis Merrillville Data Center

Merrillville,Lake County,IndianaIn permittingFirst public 2024Filing entity: Karis Acquisition, LLCLast checked Nov 10, 2026

Karis AcquisitionDeveloperNIPSCOElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: First public date
  • Still to confirm: Capacity
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Karis Merrillville Data Center is a data center project in Merrillville, Lake County, Indiana. Karis Acquisition is named as developer. It is in permitting. It was first public in 2024. No site capacity figure is published for this project.

Karis Merrillville Data Center is a data center project in Merrillville, Lake County, Indiana. Karis Acquisition is named as developer. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Merrillville, Lake County, Indiana. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

2Public records we have found
$100 millionEstimated cost
9Buildings

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Lake County, Indiana.See every project on the map

The land, to scale

One football field
177 acres, about 134 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · DecisionTown of Merrillville Plan Commission: Plan Commission approved the zone change (A-1 to CIS) for a proposed data center by unanimous voice vote 7-0, and approved a four-year zoning commitment by 6 yes votes and 1 abstention for Karis Merrillville Data CenterP4Z1-0724
  2. · FilingFiled with Town of Merrillville Plan Commission for Karis Merrillville Data CenterP4Z1-0724
  3. · New projectFirst public record of Karis Merrillville Data CenterIn permitting

Bills and laws in Indiana

All 8 in Bill Watch

Who's involved

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Town of Merrillville Plan Commission, P4Z1-0724

    Estimated cost
    $100 million
    Buildings
    9 buildings
    Stated in the filing
    177 acres

Public records

2 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Karis Merrillville Data Center?
Karis Merrillville Data Center is a data center project in Merrillville, Lake County, Indiana.
Who is developing Karis Merrillville Data Center?
Karis Acquisition is named as the developer of Karis Merrillville Data Center.
How big is Karis Merrillville Data Center?
The site covers 177 acres.
What stage is Karis Merrillville Data Center?
Karis Merrillville Data Center is in permitting. It was first public in 2024.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Merrillville Plan Commission Minutes, July 16, 2024
    Town of Merrillville
    Tier 1 · Captured 2026-11-10 · Open the source
  2. 2
    Merrillville Town Council Agenda, September 10, 2024
    Town of Merrillville
    Tier 1 · Captured 2026-11-10 · Open the source