Project File · Public records
Every public record we have for Karis Merrillville Data Center
Merrillville, Lake County, IndianaIn permittingFirst public 2024Filing entity: Karis Acquisition, LLCLast checked Nov 10, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
2 of 2 records
2024
Public decisionApprovedJul 16, 2024Town of Merrillville Plan Commission
Town of Merrillville Plan Commission, P4Z1-0724
Plan Commission approved the zone change (A-1 to CIS) for a proposed data center by unanimous voice vote 7-0, and approved a four-year zoning commitment by 6 yes votes and 1 abstention
- Estimated cost:
- $100 million
- Buildings:
- 9 buildings
- Parcel acres:
- 177 acres
Draft research, not yet verifiedLast checked Nov 10, 2026Where it says this
Minutes pp. 1-3
Recorded voteJul 16, 2024Merrillville Plan Commission
Petition P4Z1-0724, zone change from A-1 to CIS for a proposed data center (Karis Acquisition, LLC, petitioner; Indiana Land Trust Co. Tr #123026, owner)
7 yes. Brian Dering (Plan Commission Member): yes; Krisopher Mellon (Plan Commission Member): yes; Leona Chandler-Felton (Plan Commission Member): yes; Luke Rich (Plan Commission Member): yes; Margaret Uzelac (Plan Commission Member): yes; Ric Holtz (Plan Commission Member): yes; Shawn Pettit (Plan Commission Member): yes.
Draft research, not yet verifiedLast checked Nov 10, 2026Where it says this
Minutes pp. 1-3 (roll call p. 1; motion and tally p. 3)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Power and utility
Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Merrillville Plan Commission Minutes, July 16, 2024
Town of MerrillvilleTier 1 · Captured 2026-11-10 · Open the source - 2Merrillville Town Council Agenda, September 10, 2024
Town of MerrillvilleTier 1 · Captured 2026-11-10 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page