EdgeConneX New Albany campus

New Albany,Licking County,OhioUnder constructionFirst public 2025Last checked Nov 9, 2026

EdgeConneXDeveloper and operatorPowerConneXElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: First public date
  • Still to confirm: Capacity
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

EdgeConneX New Albany campus is a under-construction data center project in New Albany, Licking County, Ohio. EdgeConneX is named as operator. It was first public in 2025. Its permitted standby generators total 216 MW.

EdgeConneX New Albany campus is an under-construction data center project in New Albany, Licking County, Ohio. EdgeConneX is named as operator. Its permitted standby generators total 216 MW. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in New Albany, Licking County, Ohio. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

5Public records we have found
1Tax agreement on record
216Generator capacity, MW

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Licking County, Ohio.See every project on the map

The land, to scale

One football field
49 acres, about 37 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · FilingFiled with Ohio Power Siting Board for EdgeConneX New Albany campus26-0361-EL-BGN
  2. · DecisionOhio Power Siting Board: Certificate for a second behind-the-meter generation facility (PowerConneX II) granted; the docket carries condition-compliance filings by PowerConneX New Albany 2, LLC for EdgeConneX New Albany campus25-0302-EL-BGN
  3. · Tax dealTax agreement approved: Sales and use tax exemption (ohio rev. code section 122.175) for EdgeConnex50% exemption from the state and county sales and use taxes on computer data center equipment, term 1/1/2026 to 12/31/2035.
  4. · DecisionOhio Power Siting Board: Certificate approved for the PowerConneX 1 Generation Project, a 120 MW natural gas fired behind-the-meter generation facility co-located with the EdgeConneX data center campus in New Albany for EdgeConneX New Albany campus25-0090-EL-BLN
  5. · New projectFirst public record of EdgeConneX New Albany campusUnder construction
  6. · FilingFiled with Ohio Power Siting Board for EdgeConneX New Albany campus25-0302-EL-BGN

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Ohio HB 646: Data center tax break caps, self-power, water and rate rules

    The act covers data centers on a single parcel or contiguous, adjacent, or aggregated parcels requiring peak demand capacity greater than twenty-five megawatts at a single building or physical location; this project has no capacity figure on record, but the project's peak demand capacity at a single building or location and its parcel layout is not on record.

    “"Data center" means one or more buildings or physical facilities or infrastructure, located on a single real property parcel or on contiguous, adjacent, or otherwise aggregated real property parcels requiring peak demand capacity that is greater than twenty-five megawatts at a single building or physical location and that are used primarily or exclusively for digital information services such as the management, storage, processing, and dissemination of electronic data and information through the use of computer systems, servers, networking equipment, and related components, including equipment cooling systems, or virtual currency mining.” (Sec. 4941.01(B))

    Rule checks: Project is in Ohio. Still to check: size: unknown, who it covers: not checked

Bills and laws in Ohio

All 9 in Bill Watch

Who's involved

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Ohio Power Siting Board, 26-0361-EL-BGN

    Generator capacity
    430 MW
  • Ohio Power Siting Board, 25-0302-EL-BGN

    Generator capacity
    216 MW
  • Ohio Power Siting Board, 25-0090-EL-BLN

    Generator capacity
    120 MW

Public records

5 records found so far. 6 kinds of record are still being collected.

See every record

Questions people ask

Where is EdgeConneX New Albany campus?
EdgeConneX New Albany campus is a data center project in New Albany, Licking County, Ohio.
Who operates EdgeConneX New Albany campus?
EdgeConneX is named as the operator of EdgeConneX New Albany campus.
How big is EdgeConneX New Albany campus?
The site covers 49 acres.
What stage is EdgeConneX New Albany campus?
EdgeConneX New Albany campus is under construction. It was first public in 2025.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    PowerConneX New Albany 3 Energy Center, public meeting notice (Case 26-0361-EL-BGN)
    EdgeConneX
    Tier 2 · Captured 2026-11-09 · Open the source
  2. 2
    DIS case record for 26-0361-EL-BGN (PowerConneX, Inc.)
    Public Utilities Commission of Ohio
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    DIS case record for 25-0302-EL-BGN (PowerConneX, Inc.)
    Public Utilities Commission of Ohio
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    OPSB approves PowerConneX 1 generation project (PUCO bulletin)
    Ohio Power Siting Board
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Ohio Data Center Tax Exemption Projects Summary (Last Updated 6/10/2026)
    Ohio Department of Development
    Tier 1 · Captured 2026-11-09 · Open the source · Archived copy
  6. 6
    Data center frequently asked questions
    City of New Albany Ohio
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    City of New Albany Ohio Data Center Zoning information sheet (May 2026)
    City of New Albany Community Development Department
    Tier 1 · Captured 2026-11-08 · Open the source