Skip to content

Project File · Public records

Every public record we have for EdgeConneX New Albany campus

New Albany, Licking County, OhioUnder constructionFirst public 2025Last checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

3 of 5 records · showing votes and minutes only ·

2026

  • Public decisionUnder reviewApr 10, 2026Ohio Power Siting Board

    Ohio Power Siting Board, 26-0361-EL-BGN

    Generator capacity:
    430 MW
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    DIS case record for 26-0361-EL-BGN (opened 4/10/2026; status open); EdgeConneX public meeting notice for the PowerConneX New Albany 3 Energy Center

2025

  • Public decisionApprovedNov 20, 2025Ohio Power Siting Board

    Ohio Power Siting Board, 25-0302-EL-BGN

    Certificate for a second behind-the-meter generation facility (PowerConneX II) granted; the docket carries condition-compliance filings by PowerConneX New Albany 2, LLC

    Generator capacity:
    216 MW
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    DIS case record for 25-0302-EL-BGN (case title PowerConneX, Inc.; opened 4/2/2025; 71 docket documents)

  • Public decisionApprovedJul 24, 2025Ohio Power Siting Board

    Ohio Power Siting Board, 25-0090-EL-BLN

    Certificate approved for the PowerConneX 1 Generation Project, a 120 MW natural gas fired behind-the-meter generation facility co-located with the EdgeConneX data center campus in New Albany

    Generator capacity:
    120 MW
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    PUCO bulletin of July 24, 2025 announcing the OPSB approval in case 25-0090-EL-BLN

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Power and utility

    Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    PowerConneX New Albany 3 Energy Center, public meeting notice (Case 26-0361-EL-BGN)
    EdgeConneX
    Tier 2 · Captured 2026-11-09 · Open the source
  2. 2
    DIS case record for 26-0361-EL-BGN (PowerConneX, Inc.)
    Public Utilities Commission of Ohio
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    DIS case record for 25-0302-EL-BGN (PowerConneX, Inc.)
    Public Utilities Commission of Ohio
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    OPSB approves PowerConneX 1 generation project (PUCO bulletin)
    Ohio Power Siting Board
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Ohio Data Center Tax Exemption Projects Summary (Last Updated 6/10/2026)
    Ohio Department of Development
    Tier 1 · Captured 2026-11-09 · Open the source · Archived copy
  6. 6
    Data center frequently asked questions
    City of New Albany Ohio
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    City of New Albany Ohio Data Center Zoning information sheet (May 2026)
    City of New Albany Community Development Department
    Tier 1 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page