Project File
CyrusOne Norwalk
Norwalk,Western Connecticut Planning Region,ConnecticutOperatingFirst public 2015Filing entity: CyrusOneLast checked Nov 10, 2026
CyrusOneOperator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
CyrusOne Norwalk is an operating data center project in Norwalk, Western Connecticut Planning Region, Connecticut. CyrusOne is named as operator. It was first public in 2015. No site capacity figure is published for this project.
CyrusOne Norwalk is an operating data center project in Norwalk, Western Connecticut Planning Region, Connecticut. CyrusOne is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Norwalk, Western Connecticut Planning Region, Connecticut. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Timeline
- · New projectFirst public record of CyrusOne NorwalkOperating
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Connecticut HB 6514: Creates the data center tax incentive program (CGS 32-286), Public Act 21-1
The act covers qualified data centers with an agreement with the Commissioner of the Department of Economic and Community Development, which must make a qualified investment of at least $200 million on or before the fifth anniversary of construction first commencing (outside an enterprise or opportunity zone, for a term of not more than 20 years); this project has 4 MW on record (IT load), but the project's qualified investment, its zone status, and whether it holds a Department agreement under the program is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“NE Edge shall make, on or before the fifth anniversary of the date in which construction, rehabilitation, renovation or repair of a Qualified Data Center first commences, a Qualified Investment of at least Two Hundred Million Dollars ($200,000,000); provided, however, if the agreement entered into between NE Edge and the DECD Commissioner has a term of greater than twenty (20) years, such Qualified Investment shall be at least Four Hundred Million Dollars ($400,000,000) with a term of thirty (30) years” (Town of Bozrah host agreement, section 1.B(b), restating the Legislation requirements)
Rule checks: Project is in Connecticut. Still to check: who it covers: not checked
Bills and laws in Connecticut
- HB 5469 · Died or failedPURA licensing for colocated (behind-the-meter) suppliers serving loads of 50 MW or more
- SB 892 · Died or failedPURA proceeding to evaluate large data centers impact on the electric distribution system
- SB 245 · Died or failed · Mar 23, 2026Ends tax incentives for new data centers
- SB 1292 · Died or failed · Apr 7, 2025Quarterly energy and water reporting and efficiency standards for AI data centers (as introduced); study (as substituted)
- HB 5955 · Died or failed · Jan 22, 2025PURA proceeding to evaluate large data centers impact on distribution reliability
- HB 5926 · Died or failed · Jan 22, 2025Surcharge on data center electricity, proceeds to the residential Combined Public Benefits Charge
Who's involved
- OperatorCyrusOne
Power
Capacity, as announced or filed
- 4 MW · Nov 2026 · it_load
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is CyrusOne Norwalk?
- CyrusOne Norwalk is a data center project in Norwalk, Western Connecticut Planning Region, Connecticut.
- Who operates CyrusOne Norwalk?
- CyrusOne is named as the operator of CyrusOne Norwalk.
- What stage is CyrusOne Norwalk?
- CyrusOne Norwalk is operating. It was first public in 2015.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1
- 2Cogent service locations, Connecticut
Cogent CommunicationsTier 2 · Captured 2026-11-10 · Open the source - 3U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page