Skip to content

ConnecticutHouse2026 SessionBill

HB 5469: PURA licensing for colocated (behind-the-meter) suppliers serving loads of 50 MW or more

Official title: AN ACT CONCERNING COLOCATED ELECTRIC SUPPLIERS AND LARGE ELECTRIC LOAD CUSTOMERS.

Official text

Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.

Where it stands

Died or failed. The official record says: died in committee.

  1. Filed (done)
  2. In committee (not reached)
  3. Passed one chamber (not reached)
  4. Passed both chambers (not reached)
  5. Signed into law (not reached)
  6. In effect (not reached)
  7. Died or failed (current stage)

What it does

  • Definition

    Applies to: Suppliers serving large electric load customers behind the meter (Connecticut)

    “"Colocated electric supplier" means any person that provides, or plans to provide, electric generation services to a large electric load customer (A) through a physical connection behind such customer's point of interconnection with the electric distribution or transmission system, or (B) if both such supplier and such customer have no connection to the electric distribution or transmission system…”

    Section 1 (new CGS 16-1(a)(51)), Raised Bill No. 5469 (LCO 2300)

  • Definition · threshold 50 MW

    Applies to: Electric customers with peak demand of 50 MW or more (Connecticut)

    “"Large electric load customer" means any electric customer whose peak demand is not less than fifty megawatts…”

    Section 1 (new CGS 16-1(a)(52)), Raised Bill No. 5469 (LCO 2300)

  • Service terms

    Applies to: Colocated electric suppliers (Connecticut)

    Starts: 2026-07-01.

    “On and after July 1, 2026, no person, municipality or regional water authority shall sell, attempt to sell or otherwise provide electric generation services to a large electric load customer in a colocated or behind-the-meter arrangement unless the person, municipality or regional water authority has been issued a license by the authority to serve as a colocated electric supplier in accordance with this section…”

    Section 2 (amended CGS 16-245(b)), Raised Bill No. 5469 (LCO 2300)

Who it touches

No project we track is matched to this bill or order: its rules do not reach them, or a check found it does not apply.

Other projects we track in Connecticut (6), not affected

Who acted

  • SponsorEnergy and Technology Committee

More from Connecticut

Sources

  1. 1
    HB 5469 (2026), raised bill text, LCO No. 2300
    Connecticut General Assembly
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "HB 5469: PURA licensing for colocated (behind-the-meter) suppliers serving loads of 50 MW or more." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/ct-2026-hb-5469