County Card
Data centers in Milam County, Texas
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 2 data center projects in Milam County, Texas as of November 2026: 1 under construction and 1 expanding, totaling about 1,900 MW announced where a figure is published.
Milam County has 2 tracked data centers. Their announced capacity totals about 1,900 MW where a figure is published. Of those, 1 under construction and 1 expanding. The projects here are Riot Rockdale data center campus and SB Energy Milam County data center (Stargate). Every figure comes from the public record linked on this page.
Data center projects in Milam County
- Riot Rockdale data center campus
ExpandingRockdale700 MW announced
- SB Energy Milam County data center (Stargate)
Under construction1,200 MW announced
Who serves this place
- Not collected yet.
Places in and around Milam County
Milam County is part of Texas.
Cities and towns
- Rockdale1 data center project tracked
Nearby places
- Dallas County36 data center projects tracked
- Bexar County16 data center projects tracked
- Collin County10 data center projects tracked
- Harris County9 data center projects tracked
- Denton County7 data center projects tracked
- Ellis County7 data center projects tracked
- Medina County6 data center projects tracked
- Tarrant County6 data center projects tracked
- Haskell County3 data center projects tracked
- Pecos County3 data center projects tracked
- Reeves County3 data center projects tracked
- Williamson County3 data center projects tracked
Court cases and commission dockets in Texas (18)
Bills and laws in Texas
- SB 6 · Signed into law · Jun 20, 2025Sets grid connection and cost rules for large loads in Texas
- SB 2222 · Died or failed · Mar 25, 2025Would exempt data center property and energy equipment from property tax
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Milam County?
- Data Center Fact Check tracks 2 data center projects in Milam County as of November 2026. Of those, 1 under construction and 1 expanding.
- What is the biggest data center in Milam County?
- By announced capacity, the biggest data center in Milam County is SB Energy Milam County data center (Stargate), announced at 1,200 MW. It is under construction.
- How much power do data centers in Milam County use?
- The 2 projects tracked in Milam County have announced about 1,900 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Milam County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-tx-milam
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page