New Albany,Licking County,OhioUnder constructionFirst public 2024Last checked Nov 9, 2026

Vantage Data CentersDeveloper and operatorTurner ConstructionBuilder

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Vantage OH1 New Albany campus is a under-construction data center project in New Albany, Licking County, Ohio. Vantage Data Centers is named as operator. It was first public in 2024. It was announced at 192 MW.

Vantage OH1 New Albany campus is an under-construction data center project in New Albany, Licking County, Ohio. Vantage Data Centers is named as operator. It was announced at 192 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in New Albany, Licking County, Ohio. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

192 MWAnnounced capacity
3Public records we have found
1Tax agreement on record

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Licking County, Ohio.See every project on the map

The land, to scale

One football field
70 acres, about 53 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Vantage OH1 New Albany campusUnder construction
  2. · DecisionOhio Tax Credit Authority: Data center tax exemption approved: 50 percent for 10 years (term 1/1/2024 to 12/31/2033) for Vantage Data Centers Management Company, LLC and New Albany Data Center, LLC, in exchange for 12 FTE jobs, $1,683,000 in new annual payroll, and a $185,000,000 fixed-asset inve...
  3. · Tax dealTax agreement approved: Sales and use tax exemption (ohio rev. code section 122.175) for Vantage Data Centers Management Company, LLC and New Albany Data Center, LLC50% exemption from the state and county sales and use taxes on computer data center equipment, term 1/1/2024 to 12/31/2033.

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Ohio HB 646: Data center tax break caps, self-power, water and rate rules

    The act covers data centers on a single parcel or contiguous, adjacent, or aggregated parcels requiring peak demand capacity greater than twenty-five megawatts at a single building or physical location; this project has 192 MW announced on record, but the project's peak demand capacity at a single building or location and its parcel layout is not on record.

    “"Data center" means one or more buildings or physical facilities or infrastructure, located on a single real property parcel or on contiguous, adjacent, or otherwise aggregated real property parcels requiring peak demand capacity that is greater than twenty-five megawatts at a single building or physical location and that are used primarily or exclusively for digital information services such as the management, storage, processing, and dissemination of electronic data and information through the use of computer systems, servers, networking equipment, and related components, including equipment cooling systems, or virtual currency mining.” (Sec. 4941.01(B))

    Rule checks: Project is in Ohio; 192 MW on record (announced), threshold 25 MW (Sec. 4941.01(B)). Still to check: who it covers: not checked

Bills and laws in Ohio

All 9 in Bill Watch

Who's involved

Public records

3 records found so far. 6 kinds of record are still being collected.

See every record

Questions people ask

Where is Vantage OH1 New Albany campus?
Vantage OH1 New Albany campus is a data center project in New Albany, Licking County, Ohio.
Who operates Vantage OH1 New Albany campus?
Vantage Data Centers is named as the operator of Vantage OH1 New Albany campus.
How big is Vantage OH1 New Albany campus?
Vantage OH1 New Albany campus was announced at 192 MW of capacity. The site covers 70 acres.
What stage is Vantage OH1 New Albany campus?
Vantage OH1 New Albany campus is under construction. It was first public in 2024.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Ohio Tax Credit Authority meeting minutes, June 24, 2024
    Ohio Tax Credit Authority (Ohio Department of Development)
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Ohio Data Center Tax Exemption Projects Summary (Last Updated 6/10/2026)
    Ohio Department of Development
    Tier 1 · Captured 2026-11-09 · Open the source · Archived copy
  3. 3
    Data center frequently asked questions
    City of New Albany Ohio
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    City of New Albany Ohio Data Center Zoning information sheet (May 2026)
    City of New Albany Community Development Department
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Vantage Data Centers Breaks Ground on 192MW Campus, Enters Growing Ohio Data Center Market with Over $2 Billion Investment in Hyperscale Digital Infrastructure
    Vantage Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page