Project File
Stratos Project
Box Elder County,UtahApprovedFirst public 2026Filing entity: O'Leary DigitalLast checked Nov 8, 2026
O'Leary DigitalDeveloperMIDAPublic partner
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: City or address
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Stratos Project is an approved data center project in Box Elder County, Utah. O'Leary Digital is named as developer. It was first public in 2026. It was announced at 9,000 MW.
Stratos Project is an approved data center project in Box Elder County, Utah. O'Leary Digital is named as developer. It was announced at 9,000 MW. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Box Elder County, Utah. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Stratos ProjectApproved
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 507: Limits local incentives for large data centers outside development zones
The act covers large load data centers that are not located within a regionally significant development zone, for which a county or municipality may not offer an incentive, except project areas and agreements predating May 6, 2027; this project has 9,000 MW on record (generator capacity), but whether this project is a large load data center, whether it is located within such a zone, and whether a county or municipality offered it an incentive is not on record.
“Except as provided in Subsection (1)(b), a county or municipality may not offer an incentive for a large load data center that is not located within a zone.” (Utah Code Sec. 63N-3a-402(1)(a))
Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 76: Requires data centers to report water use before and after building
The act covers large data centers, facilities with an annual water withdrawal of 75 acre feet per year or more whose buildings total at least 10,000 square feet; this project has 9,000 MW on record (generator capacity), but the project's annual water withdrawal and its building area is not on record.
“"Large data center" means a facility with an annual water withdrawal of 75 acre feet per year or more that: (i) houses a group of networked server computers in one physical location to disseminate, manage, and store data and information as the primary service of the facility; (ii) consists of one or more buildings that in total equals or exceeds 10,000 square feet;” (Utah Code Sec. 73-5-8.3(1)(d), as enacted by H.B. 76, Section 2)
Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah SB 132: Sets cost and service rules for electric loads over 100 megawatts
The act covers large-scale service requests to a qualified electric utility, for new service expected to reach a cumulative demand of 100 megawatts or greater within five years, or added service expected to raise a customer's total by 100 megawatts or greater within five years; this project has 9,000 MW on record (generator capacity), but whether this project has submitted a large-scale service request and its expected demand within five years of the requested start date is not on record.
“"Large-scale service request" means a request submitted to a qualified electric utility for: (a) new electric service that is expected to reach a cumulative demand of 100 megawatts or greater within five years of the requested initial start date; or (b) additional electric service that is expected to increase a customer's total service level by 100 megawatts or greater within five years of the requested start date for the additional electric service.” (Definitions enacting Utah Code Title 54, Chapter 26, S.B. 132 enrolled text)
Rule checks: Project is in Utah; 9,000 MW on record (announced), threshold 100 MW (Definitions enacting Utah Code Title 54, Chapter 26, S.B. 132 enrolled text). Still to check: dates: not checked, who it covers: not checked
Bills and laws in Utah
- HB 76 · In effect · May 6, 2026Requires data centers to report water use before and after building
- HB 507 · Signed into law · Mar 25, 2026Limits local incentives for large data centers outside development zones
- SB 132 · In effect · May 7, 2025Sets cost and service rules for electric loads over 100 megawatts
Who's involved
- DeveloperO'Leary Digital
- Public partnerMIDA
Power
Capacity, as announced or filed
- 3,000 MW · Phase OneMay 2026 · generator_capacity
- 9,000 MW · Full buildoutMay 2026 · generator_capacity
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Stratos Project?
- Stratos Project is a data center project in Box Elder County, Utah.
- Who is developing Stratos Project?
- O'Leary Digital is named as the developer of Stratos Project.
- How big is Stratos Project?
- Stratos Project was announced at 9,000 MW of capacity. The site covers 40,000 acres.
- What stage is Stratos Project?
- Stratos Project is approved. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Stratos Project Area
Military Installation Development Authority (MIDA)Tier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page