Project File
Servpac MTP Data Center
Mililani Town,Honolulu County,HawaiiExpandingLast checked Nov 8, 2026
ServpacDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Still to confirm: Capacity
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Servpac MTP Data Center is an expanding data center project in Mililani Town, Honolulu County, Hawaii. Servpac is named as operator. No site capacity figure is published for this project.
Servpac MTP Data Center is an expanding data center project in Mililani Town, Honolulu County, Hawaii. Servpac is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Mililani Town, Honolulu County, Hawaii. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Hawaii HCR 206: Requests a state working group study of large data centers of 5 MW or more and their impacts
The act covers large data centers requiring electricity of five megawatts or more in instantaneous demand, whose impacts the requested working group would study; the resolution sets no operating rule for a project; this project has no capacity figure on record, but the project's instantaneous demand, and the resolution in any case requests a study rather than setting a condition a project record could meet is not on record. Status part: the resolution's status (Resolution adopted in final form.) is the status part; the text part is that it requests a study and sets no project-level condition. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“the Hawaii State Energy Office is requested to convene a working group to study the potential impacts of large data centers requiring electricity of five megawatts or more in instantaneous demand on Hawaii's electric utilities, ratepayers, natural resources, and climate goals;” (HCR 206, HD 1 text, first RESOLVED clause)
Rule checks: Project is in Hawaii. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Hawaii HR 196: Requests a state working group study of large data centers of 5 MW or more and their impacts
The act covers large data centers requiring electricity of five megawatts or more in instantaneous demand, whose impacts the requested working group would study; the resolution sets no operating rule for a project; this project has no capacity figure on record, but the project's instantaneous demand, and the resolution in any case requests a study rather than setting a condition a project record could meet is not on record. Status part: the resolution's status (Resolution adopted in final form.) is the status part; the text part is that it requests a study and sets no project-level condition. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“the Hawaii State Energy Office is requested to convene a working group to study the potential impacts of large data centers requiring electricity of five megawatts or more in instantaneous demand on Hawaii's electric utilities, ratepayers, natural resources, and climate goals;” (HR 196, HD 1 text, first RESOLVED clause)
Rule checks: Project is in Hawaii. Still to check: who it covers: not checked
Bills and laws in Hawaii
- SR 90 · Passed one chamber · May 12, 2026Requests a state working group study of large data center impacts on utilities, ratepayers, resources and climate goals
- HCR 206 · Passed both chambers · Apr 27, 2026Requests a state working group study of large data centers of 5 MW or more and their impacts
- SCR 95 · Passed one chamber · Apr 10, 2026Requests a state working group study of large data center impacts on utilities, ratepayers, resources and climate goals
- HR 196 · Passed one chamber · Apr 9, 2026Requests a state working group study of large data centers of 5 MW or more and their impacts
Who's involved
- Developer and operatorServpac
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Servpac MTP Data Center?
- Servpac MTP Data Center is a data center project in Mililani Town, Honolulu County, Hawaii.
- Who operates Servpac MTP Data Center?
- Servpac is named as the operator of Servpac MTP Data Center.
- What stage is Servpac MTP Data Center?
- Servpac MTP Data Center is expanding.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Honolulu data center market page, carrying Servpac’s February 2026 expansion news item
Servpac (company announcement as republished by Baxtel)Tier 4 · Captured 2026-11-08 · Open the source - 2U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source - 3EIA Form 861, Service Territory file, 2025 (final)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-11 · Open the source · Archived copy
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page