HawaiiHouse of RepresentativesThirty-Third Legislature, Regular Session of 2026Resolution
HCR 206: Requests a state working group study of large data centers of 5 MW or more and their impacts
Official title: REQUESTING THE HAWAII STATE ENERGY OFFICE TO CONVENE A WORKING GROUP TO STUDY THE POTENTIAL IMPACTS OF LARGE DATA CENTERS ON HAWAII'S ELECTRIC UTILITIES, RATEPAYERS, NATURAL RESOURCES, AND CLIMATE GOALS
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Passed both chambers as of Apr 27, 2026. The official record says: Resolution adopted in final form..
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (current stage)
- Signed into law (not reached)
- In effect (not reached)
What it does
Definition · threshold 5 MW instantaneous demand
Applies to: large data centers (Hawaii)
“large data centers requiring electricity of five megawatts or more in instantaneous demand…”
HCR 206, HD 1 text, first RESOLVED clause
Who it touches (2)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DRFortress Honolulu
The act covers large data centers requiring electricity of five megawatts or more in instantaneous demand, whose impacts the requested working group would study; the resolution sets no operating rule for a project; this project has no capacity figure on record, but the project's instantaneous demand, and the resolution in any case requests a study rather than setting a condition a project record could meet is not on record. Status part: the resolution's status (Resolution adopted in final form.) is the status part; the text part is that it requests a study and sets no project-level condition. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“the Hawaii State Energy Office is requested to convene a working group to study the potential impacts of large data centers requiring electricity of five megawatts or more in instantaneous demand on Hawaii's electric utilities, ratepayers, natural resources, and climate goals;” (HCR 206, HD 1 text, first RESOLVED clause)
Rule checks: Project is in Hawaii. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Servpac MTP Data Center
The act covers large data centers requiring electricity of five megawatts or more in instantaneous demand, whose impacts the requested working group would study; the resolution sets no operating rule for a project; this project has no capacity figure on record, but the project's instantaneous demand, and the resolution in any case requests a study rather than setting a condition a project record could meet is not on record. Status part: the resolution's status (Resolution adopted in final form.) is the status part; the text part is that it requests a study and sets no project-level condition. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“the Hawaii State Energy Office is requested to convene a working group to study the potential impacts of large data centers requiring electricity of five megawatts or more in instantaneous demand on Hawaii's electric utilities, ratepayers, natural resources, and climate goals;” (HCR 206, HD 1 text, first RESOLVED clause)
Rule checks: Project is in Hawaii. Still to check: who it covers: not checked
Who acted
- SponsorLOWEN, AMATO, BELATTI, GRANDINETTI, KAPELA, KEOHOKAPU-LEE LOY, KUSCH, MARTEN, MIYAKE, PERRUSO, POEPOE, TEMPLO, TODD
More from Hawaii
- SR 90 · Passed one chamberRequests a state working group study of large data center impacts on utilities, ratepayers, resources and climate goals
- SCR 95 · Passed one chamberRequests a state working group study of large data center impacts on utilities, ratepayers, resources and climate goals
- HR 196 · Passed one chamberRequests a state working group study of large data centers of 5 MW or more and their impacts
Sources
- 1
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "HCR 206: Requests a state working group study of large data centers of 5 MW or more and their impacts." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/hi-2026-hcr-206
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page